Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/22/2025 | ENGR Engineering Final | Not Ready | Not ready, Temp pole needs to go, Fenced area needs to go, Porta Jon needs to go, Landscaping needs to go, Stabilizing construction areas need to be done, Parking lot needs to be cleaned, Storage lot needs to be cleaned, All trash needs to be cleaned up, Landscaping inspection needs to be scheduled. There has to be no standing water in the water harvesting area. |
|
| 08/27/2025 | ENGR Engineering Final | Partial Pass | Building is good and ready. TCO4 can be acquired. | |
| 09/03/2025 | ENGR Engineering Final | Not Ready | ||
| 09/26/2025 | ENGR Engineering Final | Passed |