Permit: T22CM01378

Parcel: 13727991E


Addresses:

6430 S COMMERCE CT


Inspection Status: Re-inspection required

Inspection History: COT - LCEL - Electrical Final 

Permit Number - T22CM01378

Inspection Description - COT - LCEL - Electrical Final 

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
04/11/2025 COT - LCEL - Electrical Final  Re-inspection required 4-11-25, called # on account and spoke with a woman who said Tim was on lunch. Arrived on site at 1028am, office was locked. Left site at 1035am.
04/14/2025 COT - LCEL - Electrical Final  Partial Pass 4-14-25, electrical intermediate inspection for 1st floor. Majority of ceiling lights are complete together with receptacles having been up and are properly grounded. Okay to continue with construction at progress areas.
06/17/2025 COT - LCEL - Electrical Final  Partial Pass 6-17-25: electrical intermediate inspection on both floors. Many of the junction boxes are labeled on 1st floor, lights, receptacles have been installed and grounded. 2nd floor has continuous construction-electricians are still working on pulling wires, labelling junction boxes, adding receptacle covers, etc..
07/01/2025 COT - LCEL - Electrical Final  Partial Pass 4-11-25, called # on account and spoke with a woman who said Tim was on lunch. Arrived on site at 1028am, office was locked. Left site at 1035am.

4-14-25, electrical intermediate inspection for 1st floor. Majority of ceiling lights are complete together with receptacles having been up and are properly grounded. Okay to continue with construction at progress areas.
6-17-25: electrical intermediate inspection on both floors. Many of the junction boxes are labeled on 1st floor, lights, receptacles have been installed and grounded. 2nd floor has continuous construction-electricians are still working on pulling wires, labelling junction boxes, adding receptacle covers, etc..
7/1/25: intermediate inspection passed at second floor.
07/31/2025 COT - LCEL - Electrical Final  Re-inspection required 7.31.2025
1st Floor
Electrical room - j boxes need label, exhaust fans for mechanical/fire not completed.
1st floor hall - j boxes needs label,
Driveway room - j boxes need label,
West 1st floor - j boxes need label,
West side electrical room #2 - half inch ko, cover plates

2nd Floor hall - j boxes needs label
North hall - j boxes need label
South hall - j boxes need label
Northside - panel H2B & L2B need covers on blanks, cap spare conduit off panel L2B
08/05/2025 COT - LCEL - Electrical Final  Re-inspection required Re inspect fuses for mini splits on roof. Raise seal tight off of roof. West end of driveway hall missing labeling on j boxes and ko seals. 8/5/2025
08/08/2025 COT - LCEL - Electrical Final  Passed 8-8-25: electrical final approved.