Permit: T22CM01378

Parcel: 13727991E

Inspection Status: Not Ready

Inspection History: COT - LCPL - Plumbing Progress 

Permit Number - T22CM01378

Inspection Description - COT - LCPL - Plumbing Progress 

Inspection Status - Not Ready

Date Description Inspector Results Comments
05/13/2024 COT - LCPL - Plumbing Progress  Not Ready 5/13/24: not ready needed information on sewer connection
07/23/2024 COT - LCPL - Plumbing Progress  Not Ready 5/13/24: not ready needed information on sewer connection
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.
07/26/2024 COT - LCPL - Plumbing Progress  Canceled Canceled per contractor. 7/26/2024
07/29/2024 COT - LCPL - Plumbing Progress  Canceled
08/01/2024 COT - LCPL - Plumbing Progress  Partial Pass 5/13/24: not ready needed information on sewer connection
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.

Canceled per contractor. 7/26/2024
7/29/24: Canceled by Erich
8/1/24: domestic water tie in per plans ok to backfill. Shading required
08/08/2024 COT - LCPL - Plumbing Progress  Partial Pass 5/13/24: not ready needed information on sewer connection
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
6/7/24: partial approval from manhole to clean out at tie-in. Air pressure conducted and passed.
7/23/24: called Erich at 6:55am (no answer, left message stating I was in route for inspection), arrived on site at 7:03am called Erich (no answer), not ready.

Canceled per contractor. 7/26/2024
7/29/24: Canceled by Erich
8/1/24: domestic water tie in per plans ok to backfill. Shading required
Partial approval for site sewer line from manhole to cleanout only OK to cover cover at your own wrist. No leak test has been performed at this time. Air test to be done after manhole is installed.
8/8/24: plumbing underground at rooms 102,103,106 passed. Ok to backfill.