Permit: T20CM01263
Permit Details
Apply Date:
02/25/2020
Applicant:
N/A
Description:
AIR CONDITIONED SELF STORGE FACILITY
Contractors:
- T L W CONSTRUCTION INC ,
Permit Reviews
Permit Number - T20CM01263
Permit Status: C of o
Permit Description: AIR CONDITIONED SELF STORGE FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/13/2021 | REVISION - - 1ST | 02/22/2021 | COMPLETED |
| 02/22/2021 | RESUBMITTAL | 03/09/2021 | COMPLETED |
| 02/25/2020 | PLANS OK TO SUBMIT - COMM | 02/25/2020 | COMPLETED |
| 02/25/2020 | COMMERCIAL - NEW | 06/28/2020 | COMPLETED |
| 06/28/2020 | RESUBMITTAL - TI ALL | 08/26/2020 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM01263
Permit Description: AIR CONDITIONED SELF STORGE FACILITY
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/19/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | 2015- Approved for the remaining West half of the building, okay to pour foundations and basement slab |
| 07/08/2021 | BUILDING - PROGRESS | TGAUSP | Approved | Partial approval for 1st floor deck, okay to pour 1st floor |
| 08/23/2021 | REINFORCED MASONRY PRE-GROUT | TGAUSP | Approved | Partial approval for top of wall at all 4 stair and elevator towers |
| 10/22/2021 | SITE - SEWER | TGAUSP | Approved | Approved for 8” sewer line approximately 500’ to Pima County approved tie in at main line. Okay to backfill |
| 10/25/2021 | FRAMING | TGAUSP | Approved | Partial Approval for all 1st floor walls and 2nd floor otter storage unit walls, pending the non bearing partitions between the storage units |
| 11/03/2021 | ROOF NAILING | TGAUSP | Approved | Approved, metal roofing |
| 11/15/2021 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Partial approval for secondary conduits from the south end of building to the transformer location, okay to backfill progress areas |
| 12/08/2021 | PLUMBING - ROOF DRAINS | TGAUSP | Approved | Approved |
| 01/26/2022 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 03/04/2022 | STUCCO MESH | TGAUSP | Approved | Approved, okay to stucco and finish exterior |
| 05/27/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO |
| 05/27/2022 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send ECO Clearance to TEP for the construction power |
| 06/15/2022 | BUILDING ABOVE CEILING | TGAUSP | Approved | NA |
| 06/23/2022 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | Not Applicable. |
| 06/23/2022 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 06/23/2022 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 06/23/2022 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Approved |
| 06/23/2022 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Approved |
| 06/23/2022 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
| 06/23/2022 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved |
| 06/23/2022 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
| 06/23/2022 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 06/23/2022 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
| 06/23/2022 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 06/23/2022 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 06/28/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved |
| 06/28/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved |
| 08/10/2022 | ENGINEERING - FINAL | MHERNANDEZ | Approved | APPROVED |
| 08/12/2022 | PLUMBING - FINAL | ESTEVENS | Approved | Approved |
| 08/12/2022 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
| 08/15/2022 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/15/2022 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 08/15/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 08/23/2022 | CERTIFICATE OF OCCUPANCY | aruiz | Approved | |
| 08/23/2022 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED, ALL CONDITIONS APPROVED |
| 08/23/2022 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF FINAL AIR BALANCE REPORT COMPLETED |