Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2022 |
BUILDING - PROGRESS |
|
Approved |
Approved |
| 07/08/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial approval for 1st floor deck, okay to pour 1st floor |
| 04/30/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
NSPECTOR TGAUSP PLACED INSPECTION IN 04/30/21. INSPECTOR TGAUSP PLACED INSPECTION IN PA 07/08/21. |
| 04/27/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial Approval for cast in place Basement walls, West side Gridline 9-4 and East side Gridline 10-22 (SI report attached) |