Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 04/19/2021 |
BUILDING PRE-SLAB |
|
Approved |
2015- Approved for the remaining West half of the building, okay to pour foundations and basement slab |
| 04/09/2021 |
BUILDING PRE-SLAB |
|
Partial Approval |
- Partial Approval for 100’ SE basement/ret wall (cast in place) |
| 03/30/2021 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial Approval-PA for East 1/2 of building, okay to pour. |
| 03/19/2021 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
|