Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 06/28/2022 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Approved |
| 03/03/2022 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial for trash enclosure foundations, okay to pour |
| 01/31/2022 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Approved foundation and stem at front sidewalk to building |
| 04/19/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Approved for the remaining West half of the building, including Stairwell |
| 04/15/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial Approval for 80’ of East end basement/retaining wall |
| 04/13/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial Approved-PA for 150’ of the NE wall (poured in place) |
| 04/07/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
NOT READY, NO CONTACT INFORMATION, LEFT MESSAGE WITH DESIGNER, NO CALL BACK |
| 03/31/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Cancelled |
Cancelled by Contractor |
| 03/30/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial Approval-PA for East 1/2 of building basement to include East side stair |
| 03/24/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partially Approved-PA for Elevator pit only, okay to pour |
| 03/19/2021 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL PA FOR ELEVATOR PIT ONLY OK TO POUR |