Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2022 |
ELECTRIC - UNDERGROUND |
|
Approved |
Approved |
| 04/07/2022 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial for underground conduits from Transformer to SES location (approx. 300’), okay backfill and place concrete at the transformer location |
| 11/15/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial approval for secondary conduits from the south end of building to the transformer location, okay to backfill progress areas |
| 11/09/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial for secondary conduits from the south end of building approximately 90’ to south east corner of building, okay to backfill progress areas |