Permit: T12CM00376
Permit Details
Apply Date:
02/13/2012
Applicant:
JAMES BRUNER
Description:
RETAIL
Contractors:
- ROCHE CONSTRUCTORS INC ,
Permit Reviews
Permit Number - T12CM00376
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/13/2012 | PLANS OK TO SUBMIT - COMM | 02/13/2012 | COMPLETED |
02/13/2012 | COMMERCIAL - NEW | 03/09/2012 | COMPLETED |
03/09/2012 | RESUBMITTAL | 04/02/2012 | COMPLETED |
04/02/2012 | RESUBMITTAL | 06/05/2012 | COMPLETED |
05/13/2013 | REVISION - - 3RD | 06/04/2013 | COMPLETED |
06/05/2012 | OTHER | 06/20/2012 | COMPLETED |
06/20/2012 | RESUBMITTAL | 06/22/2012 | COMPLETED |
06/22/2012 | RESUBMITTAL | 06/25/2012 | COMPLETED |
07/11/2013 | REVISION - - 4TH | 07/18/2013 | COMPLETED |
07/31/2012 | REVISION - - 1ST | 09/25/2012 | COMPLETED |
09/20/2012 | REVISION - - 2ND | 10/11/2012 | COMPLETED |
10/11/2012 | REVISION - - 2ND | 10/25/2012 | COMPLETED |
10/25/2012 | REVISION - - 2ND | 11/05/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM00376
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/13/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM00376
Permit Description: RETAIL
Total Completed Inspections - 54
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2012 | ELECTRIC - UFER | RMORENO | Approved | CALLED AT 12:38PM HAVING TROUBLE WITH HIS COMPUTER GETTING IT IN |
09/12/2012 | ELECTRIC - UNDERGROUND | JBURGE | Approved | 1" TAMPER DEVICE (SOUTH) -3-1" SITE LIGHTING 3"- SECURITY CAMERA: 2-1" IRRIGATION CONDUITS (STUB-UPS_ OK TO COVER PROGRESS AREAS |
09/17/2012 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | CORRECTIONS OK TO COVER * |
09/19/2012 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | TYPE STUBS INTO BUILDING WITH TEST OK |
10/08/2012 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | PLYWOOD SHEATHING (EAST SIDE) MAIN ENTRY PARAPET AREA OK TO COVER PROGRESS AREA |
10/11/2012 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
10/11/2012 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
10/26/2012 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | DELI AREA WALLS OK |
10/29/2012 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | |
11/07/2012 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | RT UNITS #1,4,5,6,13,15-OK TO WRAP INSULATE |
11/21/2012 | PLUMBING - ROOF DRAINS | JBURGE | Approved | MAIN DRAINS AND OVERFLOW DRAINS- OK TO COVER |
11/27/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 11 CAISSON LIGHT POLE CAGES |
11/27/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | RT-15: RESTROOMS; RT-13 PERSONNEL OFFICES OK TO INSULATE DUCT WORK |
12/03/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/04/2012 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | 1. EAST WALL POWER AND LOW VOLTAGE 2. WEST WALL SOUTH OF FRONT ENTRANCE OK |
12/05/2012 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | 1 MIN FLUSH |
12/07/2012 | ELECTRIC - PROGRESS | RMORENO | Approved | 1) PANELS H2A, H2B, L201. L2DE 2) GROUNING ELECTRODE4 AT EDCI SWITCH GEAR L1U, L1D1-2, H/A MAIN BONDING JUMP 3) BUILDING BONDING STEEL LEFT TO INSPECT 4) LITE POLES UNDER GROUND OK 5) PRESSURE TEST 60LBS AT DRY PRODUCE PREP AND BAKERY DELI AND BACK BATH ROOMS OK |
12/07/2012 | PLUMBING - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
12/14/2012 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
12/17/2012 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :*3 WATER DRAINAGE AREAS IN SITE WALLS OK TO GROUT AND CAP PROGRESS AREAS |
12/18/2012 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* PARKING LOT POLE LITES ALL OK FIRE PUMP TO BE BONDED |
12/18/2012 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
12/18/2012 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
12/19/2012 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :*COMPACTOR SLAB AT GL:L/1.5-2.2;BATTERY STORAGE PAD AT GL:L/1 OK TO POUR PROGRESS AREAS. |
12/20/2012 | FRAMING | JBURGE | Approved | framing enry vertibule;AP office return storage ok to sheetrock |
01/08/2013 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
01/10/2013 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
02/07/2013 | TEP CLEARANCE - AM | RMORENO | Approved | OK TO ENERGIZE ECO COMMERCIAL 1 METER |
02/19/2013 | FIRE - KITCHEN EXH HOOD FINAL | CSCHULTZ | Approved | |
02/19/2013 | FIRE SPKLR - OH PIPING & HYDRO | CSCHULTZ | Approved | |
03/08/2013 | NPPO - FINAL | MRUSSO | Approved | |
03/08/2013 | SIGN - FINAL | MRUSSO | Approved | |
04/29/2013 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
04/29/2013 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
05/02/2013 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
05/02/2013 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
05/02/2013 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
05/02/2013 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
05/02/2013 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
05/17/2013 | FIRE - ALARM FINAL | WMOTTO | Approved | |
05/23/2013 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
06/13/2013 | MECHANICAL - HOODS | BBENEDON | Approved | IVRS - Inspection :* |
06/19/2013 | FIRE - FINAL | CBASALDU | Approved | |
06/19/2013 | FIRE - HYDRANTS | CBASALDU | Approved | |
06/24/2013 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
06/24/2013 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
06/25/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
06/25/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
07/03/2013 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* |
07/10/2013 | MECHANICAL - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
07/11/2013 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
07/12/2013 | BUILDING - FINAL | JBURGE | Approved | OK FOR C OF O PER RON BOOSE |
07/12/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
07/15/2013 | OUTDOOR LIGHTING FINAL | RBOOSE | Approved | Cut sheets provided for installed lamps do not match lamps on approved lighting plan. |