Permit: T10CM00802
Permit Details
Apply Date:
03/29/2010
Applicant:
N/A
Description:
NEW ELEPHANT EXHIBIT
Contractors:
- ASHTON COMPANY INC CONTRACTORS A
Permit Reviews
Permit Number - T10CM00802
Permit Status: Final
Permit Description: NEW ELEPHANT EXHIBIT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/29/2010 | PLANS OK TO SUBMIT - COMM | 04/01/2010 | COMPLETED |
03/29/2010 | SITE | 07/09/2010 | COMPLETED |
03/29/2010 | COMMERCIAL NEW | 07/09/2010 | COMPLETED |
05/11/2011 | REVISION - - 1ST | 05/24/2011 | COMPLETED |
07/09/2010 | RESUBMITTAL - SITE ALL | 09/10/2010 | COMPLETED |
07/09/2010 | RESUBMITTAL - TI ALL | 09/10/2010 | COMPLETED |
08/02/2011 | REVISION - - 2ND | 09/15/2011 | COMPLETED |
08/02/2011 | REVISION - SITE | 09/15/2011 | COMPLETED |
09/10/2010 | RESUBMITTAL | 11/23/2010 | COMPLETED |
09/10/2010 | RESUBMITTAL - SITE | 12/17/2010 | COMPLETED |
09/23/2011 | REVISION - - 2ND | 11/10/2011 | COMPLETED |
09/23/2011 | REVISION - SITE | 11/10/2011 | COMPLETED |
11/10/2011 | REVISION - - 2ND | 12/01/2011 | COMPLETED |
11/23/2010 | RESUBMITTAL | 12/17/2010 | COMPLETED |
12/01/2011 | REVISION - - 2ND | 12/06/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00802
Permit Status: Final
Permit Description: NEW ELEPHANT EXHIBIT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/29/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM00802
Permit Description: NEW ELEPHANT EXHIBIT
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/05/2011 | FIRE - HYDRANTS | DSIWARSKI | Approved | |
04/20/2011 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
08/24/2011 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* INSTALL OF (3) YARD HYDRANTS AT VISITOR PULL OFF. |
09/22/2011 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* 1) ABOVE HARD LIDS IN ELEPHANT BARN RESTROOMS |
09/29/2011 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
10/03/2011 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
10/18/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
10/20/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
10/20/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
11/04/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
11/08/2011 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED FOR "NEW ELEPHANT EXHIBIT SERVICE" PER D. SANTACRUZ |
11/14/2011 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) METAL ROOF SYSTEM WELDS TO STEAL FRAMING OK TO COVER PROGRESS AREAS |
11/17/2011 | FRAMING | MHENSON | Approved | IVRS - Inspection :* 1) LAST OF CLEAR STORYS AND CEILING DROPS |
11/22/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* 1) 2" GAS DIVERTED TO WEST SIDE OF ADMIN. BLDG LINE WILL BE MEDIUM PRESSURE SUPPLIED BY SW GAS-SUBJECT TO REVISED PLAN-OK TO COVER |
12/01/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) HOT AND COLD TO HOSE BIBB-3/4" COLD TO ELEPHANT DRINKER OK AT ELEPHANT BARN |
12/05/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) THE AGGREGRATE CROSS SECTION AT AREA OF VENTING MUST EQUAL THE LONGEST REQUIRED TO BLDG DRAIN, NO VENT ALLOWED UPSTREAM FROM G.W. VALVE 2) TOTAL VENTING FOR SEWER TO BE MINIMUM 3" |
12/06/2011 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
12/09/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) BEDROOM #2-PLYWOOD SHEATHING ON CEILING AREAS OK TO COVER |
12/19/2011 | ELECTRIC - PROGRESS | RMORENO | Approved | IVRS - Inspection :* 1) ELEPHANT HYDROLIC CONTROL PIPE RUN OK |
12/27/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) 11 CASSIONS WEST 1/2 COMPLETE |
01/12/2012 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
01/13/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
01/18/2012 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
01/18/2012 | TEP CLEARANCE - AM | JWEATHER | Approved | DGC CLEARED FOR "PHOTOVOLTAIC SYSTEM" PER D. SANTACRUZ |
01/23/2012 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
01/23/2012 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
02/02/2012 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
02/03/2012 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
02/03/2012 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
02/03/2012 | NPPO - FINAL | RLEDONNE | Approved | NPPO NA TO THIS ACTIVITY. |
02/03/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
02/03/2012 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
02/08/2012 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
02/10/2012 | FIRE - FINAL | WMOTTO | Approved | |
02/13/2012 | ENGINEERING - FINAL | RLEDONNE | Approved | |
02/17/2012 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
02/17/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |