Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10CM00802

Parcel: 12620001C


Addresses:

3400 E ZOO CT


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T10CM00802

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
01/13/2012 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
1) FENCE BARRIER CASSION FOOTINGS
01/09/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 2 FENCE BARRIER CAISSON FOOTINGS-OK TO POUR FOOTINGS
01/05/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 5 BARRIER FENCE POST FOOTINGS; DETAIL #OS-402 OK TO POUR FOOTINGS
12/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 11 CASSIONS WEST 1/2 COMPLETE
12/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 13 CASSION FOOTINGS AS PER DETAIL 313 CABLE BARRIER OK TO POUR PROGRESS AREAS
12/08/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) CANCELLED BY CONTRACTOR
12/01/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 9 DIVIDING CASSIONS AND 2 SWING GATE REBAR OK
11/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) CASSIONS AT EXHIBIT DIVISION
11/28/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
11/22/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 6-8' CAISSONS 11-5' PORCH CAISSONS EXHIBIT DIVISION
11/15/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 25 REBAR GAGES OK
11/02/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) PARTIAL 2 CASSIONS AT EAST SIDE OF ELEPHANT BARN
11/01/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 4 CASSIONS SOUTHEAST CORNER OF BARN
2) CURB AT SLIDE GATE
10/28/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 5 CASSIONS SOUTH SIDE OF ELEPHANT BARN
10/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 9 CASSIONS ON EAST SIDE OF ELEPHANT BARN
10/20/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
10/19/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 7 CAISSIONS AT NORTH EAST CORNERS OF ELEPHANT BARN
10/03/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 11 AT CAISSION COLUMN FOOTINGS (CAGES)
1) STEM WALL (STEEL BOLLARD CURB) DEAIL #7 PAGE 2S-301 AT ERD BLDG OK TO POUR PROGRESS AREAS
09/28/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ERD CURBS AS MARKED ON PLAN
09/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 28 CASSIONS OK RECALL WHEN SET
2) EAST SHOT CRETE SCREEN WALL FOOTINGS COMPLETE
09/15/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST TERMINATE MOUND FOOTING AND STAIRS AT KOPJE
09/12/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTING FOR WEST TERMINATE MOUND STRUCTURE REINFORCEMENT STEEL OK PER RFI-30D DETAIL 29A
07/29/2011 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - RI canceled
07/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
07/22/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) CMU FOOTINGS AT COPJE
2) CURBS FOR BEDROOM 2 AND COMMUNITY ROOM
07/21/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) MISSING REBAR AND OVER SPACED
07/19/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ERD GRADE BEAMS
2) LAST EDR CASSION
07/18/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
07/14/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
NEEDS CORNER ? AND ENGINEER OK ON 3 PC STIRRUP NOT HOOKED TOP TO BOTTOM
07/13/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELEPHANT POOL COMPLETE
07/12/2011 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - RI canceled
07/08/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) PLANTER FOOTING, 1 CAISSON AT ERD CENTER
07/07/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) POOL COMPLETE
07/06/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 3 CAISSONS EAST SIDE OF ERD
06/29/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 5 CASSIONS RECALL WHEN SET
2) NEED RFI THAT UNTREATED PLYWOOD BOX INSTEAD OF BACK FILL IS OK
3) IF POURED SOLID OK TO POUR WITH SPECIAL INSPECTION
06/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) RINO MOAT FOOTING-CONFOMATEC INSPECTED
06/24/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) CAISSONS TO HAVE #12 VERT AND ALTERNATE STIRRUP HOOKS
06/20/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 2 PONY WALL FOOTING SOUTHWEST SIDE OF ELEPHANT BARN
06/16/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) PONY WALL FOOTING AT MOAT, CMU WALL AT LIFT STATION
06/06/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* MUDWALLS
05/26/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) WALL "A"-8' 10" ; WALL "B" AT 12'-16'' WALL "C" 16'-20' OK TO GROUT PROGRESS AREAS
05/19/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
05/13/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COPJA PLANTER FOOTING
05/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOT REINF. FOR 8" CMU SCREEN WALL AT LSS BLDG AND AT ELEPHANT POOL-SPECIAL INSPECTED CONFORMATECH
05/06/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SCREEN WALL FOOTING AT LSS TANK OK TO POUR FOOTING
05/03/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* ROACK FOOTING AT SLIDE GATE SPECIAL INSPECTED
05/02/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* FINAL SE SHOTCRETE FOOTING
WE CORNER ROCK AND SHOTCRETE
04/25/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) TRAINING BARN COMPLETE EXCEPT POP OUTS
04/20/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST OF LSS 11' CMU WALL FOOTING
2) ELEPHANT BARN: NO PIPE TO RUN THRU FOOTING (8) OS-301 NOT READY TO POUR
04/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/12/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) PARTIAL FOOTING ALONG 22ND ST FROM 174' TO APPROX 219'-SPECIAL INSPECTED
04/11/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* REINFORCEMENT STEEL FOR FOUNDATION OF SHOT CRETE RETAINING WALL FROM 135' TO 189' FROM STARTING POINT - OK - SPECIAL BY CONFORMATECH
04/05/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*REINFORCING STEEL @ SHOTCRETE DEEPEND FOOTING AT UTILITIES (HIGH PRESURE SEWER LINE @ SOUTH OF SITE) APPROX 25 L.F. IN LENGTH - FOOTING SECTION A5 50' OR 65' EAST OFSTARING POINT. SPECIAL INSPECTION BY CONTRACTOR
04/04/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/24/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) MOAT FOOTING COMPLETE
03/16/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SHOT CRETE WALL FOOTING AT SOUTH EAST CORNER OF EXHIBIT "B" AT NORTH END-SHOT CRETE WALL IN SOUTH EAST CORNER APPROX SOUTH 60 L.F. FROM NORTH END OF WALL AT SOUTH WEST COTRNER OF EXHIBIT "A" FROM 0 TO 4' THE PERIMETER AFTER CMU WALL-SPECIAL BY CONFORMATECH
03/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) MOAT FOOTING COMPLETE
03/09/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) EAST SHOT CUTE WALL 65' FROM SOUTH EAST CORNER
02/23/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SHOT CRETE WALL FOOTING FOR SITE WALL FROM WEST END TO 140 L.F. EAST-OK
2) SPECIAL INSPECTION BY CONFORMATECH
02/17/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*