Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T10CM00802

Parcel: 12620001C


Addresses:

3400 E ZOO CT


Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Permit Number - T10CM00802

Inspection Description - PLUMBING - ROUGH, SOIL

Inspection Status - Approved

Date Description Inspector Results Comments
01/23/2012 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
12/05/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) THE AGGREGRATE CROSS SECTION AT AREA OF VENTING MUST EQUAL THE LONGEST REQUIRED TO BLDG DRAIN, NO VENT ALLOWED UPSTREAM FROM G.W. VALVE
2) TOTAL VENTING FOR SEWER TO BE MINIMUM 3"
11/14/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) PROVIDE BACKWATER VALVE TEST WITH VENT FOR DOWNSTREAM SEWER EQUAL TO REQUIRED BLDG DRAIN
08/11/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
07/26/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
06/22/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) PLEASE CALL IN LSS STRUCTURE ON PERMIT #T10CM00917
06/20/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
06/16/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) SKIMMER RETURN LINES FOR POOL OK
2) AT BOTH INTERCEPTOR AND SEWER CONNECTION OK
06/15/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) CANCELLED
06/08/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
06/07/2011 PLUMBING - ROUGH, SOIL Partial Approval 1) ADDITION ON P-14 IN STORAGE 110 PER RED LINE ON SITE AND 8 1/2" X 11 WATER TEST THRU CLEANOUT HEIGHT
05/17/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) FROM INITIAL PAGE 1 P101 SANITARY DRAINAGE UPSTREAM THRU BLDF WATER TEST THRU CLEANIOUTS
05/16/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) WATER TEST SANITARY DRAINAGE INTERIOR TO 2' EXTERIOR OF BLDG EXCEPT, HORIZONTAL VENTING REQUIRES CORRECT FITTING ORIENTATION WITH DRAINAGE NOT DRAIN ARM
05/09/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) 3/4 HOT AND COULD TO 16' HB-2 AT SOUTH/WEST
05/03/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
05/03/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* 6" WASTE FROM INITIAL PAGG IP101 TO INITIAL JUST BEFORE INTERLOPTOR WATER TEST. 6" SDR 35 BUILDING SEWER FROM 3' EXTERIOR AIR TEST TO 8" PRIVATE SEWER
04/29/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
04/27/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
04/22/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) 4" CAPPED DRAIN 75 PSI TEST
04/18/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
04/14/2011 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
04/13/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
04/12/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
04/11/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
04/07/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
04/06/2011 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) REPAIR LEAK AT NOZZLE ADAPTER SUPPLY SIDE BUSHING AND RETEST
04/05/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*NOT UNDER TEST AT 8:48AM
04/04/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
03/31/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) 10" POOL SUPPLY FROM LSS TANK TIEING INTO 10" POOL SUPPLY TO ELEPHANT POND CONTINUATION APP. 100'
2) 4" STREAM SUPPLY STUBBED 20' OUT FROM LSS TANK
03/29/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) PVC SCHEDULE 80-10" POOL DRAIN TIED INTO LSS TANK WITH 100 PSI TEST FROM THAT POINT TO (2) 10" STUB INTO (2) MAIN DRAIN BASINS, ALSO WITNESSED BY BILL ROWLEY (ASHTON)
03/24/2011 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1) 10" ELEPHANT POOL DRAIN PIPING FROM 80' FROM LSS HOLDING, OBSERVED INSTALLATION. MOVING TOWARD HOLDING PRIOR IS INSTALLED WITHOUT INSPECTION
03/23/2011 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) 10" POOL SUPPLY FROM LSS TO NOZZLES 100 PSI TEST
2) 10" SKIMMER PVC SCHEDULE 80 FROM LSS APP 100' LAYING BEDDING