Permit: T05CM02739
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2411 E FORT LOWELL RD
Address NEW:
2411 E FORT LOWELL RD
Apply Date:
06/14/2005
Applicant:
N/A
Description:
PARTIAL DEMO/ NEW ADDITION
Contractors:
- CIENAGA CANYON CONTRACTORS L L C
Permit Reviews
Permit Number - T05CM02739
Permit Status: C of o
Permit Description: PARTIAL DEMO/ NEW ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 01/17/2008 | COMPLETED |
| 01/27/2006 | RESUBMITTAL - SITE ALL | 04/21/2006 | COMPLETED |
| 04/08/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/20/2008 | COMPLETED |
| 04/18/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 04/19/2007 | COMPLETED |
| 05/20/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/20/2008 | COMPLETED |
| 06/08/2006 | RESUBMITTAL - SITE ALL | 06/14/2006 | COMPLETED |
| 06/14/2005 | PLANS OK TO SUBMIT - COMM | 06/21/2005 | COMPLETED |
| 06/14/2005 | PLANS OK TO SUBMIT - SITE | 06/14/2005 | COMPLETED |
| 06/14/2006 | RESUBMITTAL - SITE | 08/16/2006 | COMPLETED |
| 06/22/2005 | SITE | 07/19/2005 | COMPLETED |
| 06/22/2005 | 3RD PARTY REVIEW-COMMERCIAL | 08/08/2006 | COMPLETED |
| 08/08/2006 | POST 3RD PARTY REVIEW | 08/16/2006 | COMPLETED |
| 09/01/2006 | RESUBMITTAL - SITE | 09/28/2006 | COMPLETED |
| 09/01/2006 | RESUBMITTAL | 09/22/2006 | COMPLETED |
| 09/09/2008 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 09/12/2008 | COMPLETED |
| 09/22/2006 | RESUBMITTAL | 04/10/2007 | COMPLETED |
| 11/10/2005 | RESUBMITTAL - SITE ALL | 12/14/2005 | COMPLETED |
| 11/23/2007 | REVISION - SITE | 01/30/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM02739
Permit Status: C of o
Permit Description: PARTIAL DEMO/ NEW ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/14/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM02739
Permit Description: PARTIAL DEMO/ NEW ADDITION
Total Completed Inspections - 48
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/20/2007 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 06/13/2007 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/12/2007 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN ROOF SYSTEM |
| 10/16/2007 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* VALUED AT 32 THROUGHOUT |
| 10/16/2007 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO COVER SOUTH & EAST WALLS |
| 10/16/2007 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2007 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2007 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/29/2007 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | NOT READY PIPEING ONLY HAD 40 PSI ON GAUGE. |
| 10/29/2007 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* OK TO COVER |
| 11/07/2007 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | SPECIAL REQUEST INSP. - PAID BY CK#1316 1. WILL REQUIRE APPROVED PLANS 2. WILL REQUIRE REDLINES SHOW LOCATION OF TWO-WAY CLEANOUTS AT P.O.C TO EXISTING - OK TO COVER SUBJECT TO APPROVED PLAN. |
| 11/08/2007 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* PLANS CALL FOR OVERHEAD SERVICE REVISE SINGLE LINE DIAGRAM TO SHOW UNDERGROUND SERVICE AND ACTUAL SCOPE OF WORK |
| 11/14/2007 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* FOR STORMWATER PIPING AROUND EXTERIOR OF BUILDING CONTACT MIKE RUSSO @ 240-9859 PROVIDE A CITY APPROVED PLAN FOR INSPECTION |
| 11/14/2007 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* FRONT FACADE COMPLETE OK TO GROUT CMU & BRICK PLACEMENT |
| 11/20/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* - SEAL AROUND FIRE DAMPERS INSIDE SLEEVE - PROVIDE PERMISSION FROM ARCHITECT OF USING PVC INSTEAD OF COPPER - OK TO SHEETROCK CORRIDOR - PROVIDE CLEAR ACCESS TO FAN COILS SERVICE ACCESS - PROVIDE INSTALL INSTRUCTIONS FOR FIRE DAMPERS |
| 11/28/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 2ND FLOOR COMPLETE - OK TO SHEETROCK ONE SIDE; SOUTH PORCH COMPLETE - OK TO SHEETROCK |
| 11/29/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1. CONTRACTOR TO TAPE ABS WHERE IN CONTACT WITH NEUTRAL STUDS - OK TO COVER WALLS - 2ND FLOOR 2. WATER TEST EAST SIDE AND WEST OK (ROOF DRAINS) ADD HANGERS WHERE REQUIRED AND RECALL INSPECTION 3. CONTRACTOR MUST PROVIDE ACCURATE REDLINES ON ALL CHANGES TO THE PLUMBING SYSTEM BY NEXT INSPECTION OR YOU WILL BE CHARGED A REINSPECTION FEE 4. NEED TO SEE CLOSET FLANGES SECURED TO THE FLOOR |
| 11/29/2007 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 11/30/2007 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* INFORMATION FOOTING NOT ON PLAN NEED TO GET APPROVED PLAN |
| 12/04/2007 | ELECTRIC - UFER | CCLEMENS | Approved | IVRS - Inspection :* - OK UFER TO REBAR AND GROUND RODS (2) - REMOVE EXTRA CONDUCTOR AFTER GROUND ROD - G.E.C IN RIGID TO BE MADE ELECTRICALLY CONTINUOUS OR PUT IN PVC |
| 12/06/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* OK 2ND LEVEL WALL COVER - DOES NOT INCLUDE PANEL ROOM |
| 12/17/2007 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 2ND FLOOR CLASSROOMS -- OK TO TAPE & TEXTURE |
| 01/04/2008 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO SECOND FLOOR FIRST FLOOR CMU WALLS |
| 04/09/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER C. CLEMENS |
| 04/29/2008 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 04/29/2008 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 05/08/2008 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 05/08/2008 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 05/08/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 05/09/2008 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - TEMPORARY SERVICE | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - CONSTRUCTION POWER | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - SERVICE UPGRADE | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - RECONNECT | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/09/2008 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/15/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 05/15/2008 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 05/15/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/15/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/23/2008 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 07/08/2008 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/13/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* AIR BALANCE OK |
| 09/16/2008 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | |
| 09/16/2008 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* PLANS REVISED & STAMPED |
| 09/16/2008 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/16/2008 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/17/2008 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |