Permit: TD-DEV-0525-00139
Permit Details
Status:
Inspections Complete
Type:
Development Package
Address:
2524 S WILMOT RD
Address NEW:
2524 S WILMOT RD
Apply Date:
05/16/2025
Applicant:
Description:
Rev 1 - Update to basins, concrete, grating, etc, started 03.18.2026 ** Construction documents for the Fry's #33 fuel center. The site plan was approved though: TD-DEV-0724-00193.
Permit Reviews
Permit Number - TD-DEV-0525-00139
Permit Status: Inspections complete
Permit Description: Rev 1 - Update to basins, concrete, grating, etc, started 03.18.2026 ** Construction documents for the Fry's #33 fuel center. The site plan was approved though: TD-DEV-0724-00193.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/04/2025 | DEVELOPMENT PACKAGE NEW v.2 | 10/24/2025 | REQUIRES RESUBMIT |
| 11/24/2025 | DEVELOPMENT PACKAGE NEW v.3 | 12/16/2025 | APPROVED |
| 03/18/2026 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 04/16/2026 | APPROVED |
| 05/19/2025 | DEVELOPMENT PACKAGE NEW v.1 | 07/09/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0525-00139
Permit Status: Inspections complete
Permit Description: Rev 1 - Update to basins, concrete, grating, etc, started 03.18.2026 ** Construction documents for the Fry's #33 fuel center. The site plan was approved though: TD-DEV-0724-00193.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/15/2025 | Prior to Final - The dry well CC&Rs as well as dry well registration with ADWR are required prior to final. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0525-00139
Permite Description: Rev 1 - Update to basins, concrete, grating, etc, started 03.18.2026 ** Construction documents for the Fry's #33 fuel center. The site plan was approved though: TD-DEV-0724-00193.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2026 | N/A | Partial Pass | Drain pipe under the canopy is proper depth and slopes. Pipe material and size has been changed - still pending approval from Engineer. 12" HDPE used in place of 10" Sch. 80 PVC under the canopy for the roof drain conveyance. Bedding is good. Backfill at contractor's risk until material change is approved by engineer of record. | |
| 02/11/2026 | ENGR - Drainage Structures | N/A | Partial Pass | RCP has been set into place in the drywell and upstream of the Envibro system. Excavation for the Envibro system is open with shoring in place. |
| 04/10/2026 | N/A | Partial Pass | Okay to grout second lift. Send pictures of grouting and vibration. | |
| 05/15/2026 | ENGR Paving | N/A | Partial Pass | Okay to place 2” for 2nd lift. |
| 05/14/2026 | N/A | Partial Pass | Ok to backfill irrigation trenches when lines are completed. Trenches and pipes correct for laterals and mainline. Equipment correct. | |
| 05/14/2026 | N/A | Not Ready | Nothing planted. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TD-DEV-0525-00139
Permit Description: Rev 1 - Update to basins, concrete, grating, etc, started 03.18.2026 ** Construction documents for the Fry's #33 fuel center. The site plan was approved though: TD-DEV-0724-00193.
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 03/19/2026 | Consultation SITE | Passed | 3/19/26Met with contractor to go over inspections that should be called in on the DP, such as site walls and the Refuse Enclosure going forward.. | |
| 05/04/2026 | For trash and recycling enclosures | Passed | Trash enclosure is complete in accordance with approved plans. | |
| 05/13/2026 | Passed | |||
| 05/13/2026 | ENGR - Drainage Structures | Passed | ||
| 05/13/2026 | Passed | |||
| 05/13/2026 | Passed | Bollards installed per plan. | ||
| 05/13/2026 | Passed | |||
| 05/13/2026 | Passed | |||
| 05/18/2026 | ENGR Paving | Passed | On-site paving is complete in accordance with approved plans. | |
| 05/20/2026 | Passed | Irrigation system is installed in accordance with approved plans. | ||
| 05/20/2026 | Passed | Shrubs and trees are installed in accordance with approved. | ||
| 05/22/2026 | SITE - Zoning Final | Passed | Site is in conformance with zoning requirements. | |
| 05/22/2026 | Passed | All items related to striping, parking, and pedestrian circulation are complete in accordance with approved plans. | ||
| 05/27/2026 | COT - FCON - Fire - Final | Passed | ||
| 05/27/2026 | COT - ENGR - Signage Final | Passed | Site signage is complete in accordance with approved plans. | |
| 05/28/2026 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 05/28/2026 | Final inspection to ensure all landscape and water harvesting SITE | Passed | All water harvesting infrastructure is complete. | |
| 05/28/2026 | LAND Landscape Appearance & Function Final | Passed | All landscaping is complete in accordance with approved plans. |