Permit: TD-DEV-0525-00139

Parcel: 131132540


Addresses:

2524 S WILMOT RD

Inspection Status: Not Ready

Inspection History: ENGR - Drainage Structures

Date Description Inspector Results Comments
01/16/2026 ENGR - Drainage Structures Not Ready Basin A1 not installed according to plans, this will need a plan revision.
02/09/2026 ENGR - Drainage Structures Partial Pass Drywell is drilled to 85 feet, excavation for RCP upstream of Envibro system is complete, RCP not yet in place.
02/11/2026 ENGR - Drainage Structures Partial Pass RCP has been set into place in the drywell and upstream of the Envibro system. Excavation for the Envibro system is open with shoring in place.
02/19/2026 ENGR - Drainage Structures Not Ready Not ready for inspection, will reschedule.
02/24/2026 ENGR - Drainage Structures Not Ready Not ready for inspection due to wrong gasket material.
02/25/2026 ENGR - Drainage Structures Partial Pass Catchbasin at center-west of canopy is set and connected correctly, okay to backfill.
03/04/2026 ENGR - Drainage Structures Partial Pass Catchbasin at south-west of canopy is set and connected correctly, okay to backfill.
03/24/2026 ENGR - Drainage Structures Partial Pass Catchbasins 5 & 6 and manhole 1 are set and connected correctly, okay to backfill.
05/13/2026 ENGR - Drainage Structures Passed