Inspection History Details
Inspection Status: Not Ready
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2026 | Not Ready | No wall inspection needed at this time. | ||
| 02/20/2026 | Not Ready | Catch basin not ready for inspection yet. | ||
| 03/19/2026 | Partial Pass | 3/19/26 On March 6 footers for West and North walls and footer/bollards for Refuse Enclosure were passed by building. HCBU-016123-2026. Okay to grout West wall 1st lift. All grouted/reinforced cells to be vibrated. Schedule inspection on the DP when top bond beam is in place and ready to grout 2nd lift. Verified 4” bond beam in wall at 2nd course an #4 at 32” on center. |
||
| 04/08/2026 | Partial Pass | Site wall along North of site: reinforcement is correct. Okay to grout first lift. | ||
| 04/10/2026 | Partial Pass | Okay to grout second lift. Send pictures of grouting and vibration. | ||
| 05/13/2026 | Passed |