Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 02/09/2026 |
|
|
Partial Pass |
72+30 LF 18" pipe on North side from MH-1 to CB-3: placement and slope are good, okay to backfill. |
| 02/11/2026 |
|
|
Partial Pass |
Drain pipe under the canopy is proper depth and slopes. Pipe material and size has been changed - still pending approval from Engineer. 12" HDPE used in place of 10" Sch. 80 PVC under the canopy for the roof drain conveyance. Bedding is good. Backfill at contractor's risk until material change is approved by engineer of record. |
| 02/19/2026 |
|
|
Partial Pass |
Canopy roof drain tie-in: East and Center tie-in is good, okay to backfill. |
| 02/24/2026 |
|
|
Not Ready |
Not ready for inspection due to wrong gasket material. |
| 02/25/2026 |
|
|
Partial Pass |
HDPE storm drain pipe and 2 associated catch basins at north-west of site are installed properly. Okay to backfill. |
| 03/04/2026 |
|
|
Partial Pass |
Final stick of HDPE pipe connecting to catchbasin at south-west of canopy is set and connected correctly, okay to backfill. |
| 03/24/2026 |
|
|
Partial Pass |
10lf of 18" pipe between CB-6 and CB-5 plus 13lf of 18" pipe between CB-5 and MH-1 and installed correctly with proper slope, okay to backfill. |
| 05/13/2026 |
|
|
Passed |
|