Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | For trash and recycling enclosures | Partial Pass | 3/19/26 Footer passed by building on 3/6. Verts in Ends and Corners of walls will be corrected and pictures sent. Okay to build 1st lift of wall. Schedule pregrout inspection on refuse enclosure when ready. |
|
| 04/08/2026 | For trash and recycling enclosures | Partial Pass | Door anchors designed for concrete do not need additional epoxy. Need to verify elevation of slab before setting rebar, needs to be consistent with plans. | |
| 04/13/2026 | For trash and recycling enclosures | Partial Pass | Slab reinforcement and forms are correct, okay to pour slab and apron. | |
| 05/04/2026 | For trash and recycling enclosures | Passed | Trash enclosure is complete in accordance with approved plans. |