Permit: TD-DEV-0223-00141
Permit Details
Apply Date:
02/15/2023
Applicant:
Description:
*Revisison #3 started 9/9/24 *Revision #2 started (structural) 5/9/24* Revision #1 started 2/23/24 (abandon easements)* Manufacturing/Warehousing with two-story warehouse/office/shop and parking lot
Permit Reviews
Permit Number - TD-DEV-0223-00141
Permit Status: Awaiting submittal
Permit Description: *Revisison #3 started 9/9/24 *Revision #2 started (structural) 5/9/24* Revision #1 started 2/23/24 (abandon easements)* Manufacturing/Warehousing with two-story warehouse/office/shop and parking lot
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/09/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/24/2024 | REQUIRES RESUBMIT |
10/13/2023 | DEVELOPMENT PACKAGE REVIEW v.4 | 11/30/2023 | APPROVED |
09/09/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 09/24/2024 | REQUIRES RESUBMIT |
02/23/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/15/2024 | REQUIRES RESUBMIT |
04/24/2024 | DEVELOPMENT PACKAGE NEW v.1 | 04/24/2024 | APPROVED |
03/29/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 05/03/2023 | REQUIRES RESUBMIT |
06/20/2024 | DEVELOPMENT PACKAGE NEW v.2 | 07/02/2024 | APPROVED |
08/01/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 09/07/2023 | REQUIRES RESUBMIT |
02/15/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/22/2023 | REQUIRES RESUBMIT |
10/22/2024 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 11/01/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Awaiting Submittal
Permit Number: TD-DEV-0223-00141
Permite Description: *Revisison #3 started 9/9/24 *Revision #2 started (structural) 5/9/24* Revision #1 started 2/23/24 (abandon easements)* Manufacturing/Warehousing with two-story warehouse/office/shop and parking lot
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/22/2024 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | Site is under construction |
04/22/2024 | SITE - Stormwater Setup and Controls | N/A | Not Ready | They have approved plans but do not yet have the permit. Permit will be here by Wednesday of this week. |
04/11/2024 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | All setup and controls are in place and steel building underground is to begin next week. (No concerns at this time) |
04/18/2024 | COT - ENGR - Site - Assurance Release | N/A | Not Applicable | |
04/19/2024 | SITE - Stormwater Follow-up | N/A | Partial Pass | No issues or concerns at this time. Post address. And SWPPP permit. |
06/07/2024 | N/A | Partial Pass | Footing inspected and passed for pour. Perimeter on east and south. | |
08/15/2024 | SITE | N/A | Partial Pass | What are harvest area is not completed yet |
08/16/2024 | For trash and recycling enclosures | N/A | Not Ready | The trash enclosure from outside the outside on the rear wall is only 20‘8“ and is not per our approve standards. The contractor has poured the footers as directed by either the owner or the Engineer of rRcord even though it is not of the proper size. I will contact the Engineer and advise him that he’s going to have to submit and get approved drawings prior to them building any of the walls for this structure or they can remove what they have poured and redo it |
10/10/2024 | N/A | Partial Pass | Contractor pouring for curb and gutter to build the project they good to pour | |
04/19/2024 | ENGR - Drainage Structures | N/A | Not Ready | Contractor requesting building footing inspection. Tom was informed that he needs to schedule inspections from his combination permit and contact Ernie Stevens for special inspections as needed. |
Completed Inspections
Permit Status: Awaiting Submittal
Permit Number: TD-DEV-0223-00141
Permit Description: *Revisison #3 started 9/9/24 *Revision #2 started (structural) 5/9/24* Revision #1 started 2/23/24 (abandon easements)* Manufacturing/Warehousing with two-story warehouse/office/shop and parking lot
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | superintendent Tom post address and SWPPP permit information. Provide Stormwater controls as needed. Schedule regular stormwater follow up in. Keep all materials contained within the site. Schedule site inspections for underground, stormwater, piping and trash enclosure. Also water harvesting, landscaping and accessibility. Schedule utility and building inspections from your combination permit. Contact Ernie Stevens for special inspections as needed. |
|
07/15/2024 | Passed | contractors good to pour the grout and the bond beam on the 8 foot walls. The 8 foot walls have two number fours and the 6 foot walls have one number four bar. |