Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2025 | Partial Pass | contractor is continuing to build the walls for the trash enclosure. We need knockouts at the bottom for the grout to spill out at every place. There’s a piece of rebar. We need a bond but the top before they grout it. On the East End of the building, there’s a retaining wall footer, good to be poured contractor needs to furnish the City Of Tucson with the compaction test results. The test results must stay on site at all times. | ||
| 01/08/2025 | Partial Pass | Good to pour the retaining wall in the front footer | ||
| 01/10/2025 | Partial Pass | Still need to pour the floor and the apron of the refuse container. Walls of enclosure are built to plan with evidence of weep holes at bottom. Cells are filled with grout stop at top. Walls in front at street are almost complete and are built per plan. Screen Wall in front of A/C’s are built to plan. |
||
| 03/25/2026 | Partial Pass | contractors good to pour the perimeter footer wall around the site | ||
| 03/27/2026 | Partial Pass | Perimeter wall on East side: first course bond beam is in place and correct, okay to grout two courses for entire wall. | ||
| 04/06/2026 | Partial Pass | The contractor is good to grout the wall around the hole construction area at 4 foot | ||
| 06/05/2024 | Partial Pass | Footing inspected and passed for pour. Perimeter on east and south. | ||
| 06/17/2024 | Partial Pass | Contractor good to grout at 2 foot wall for the first part of the wall bond beam is in place using number four bar | ||
| 07/02/2024 | Partial Pass | Contractors OK to grout from the 2 foot to 4 foot second grouting | ||
| 07/15/2024 | Passed | contractors good to pour the grout and the bond beam on the 8 foot walls. The 8 foot walls have two number fours and the 6 foot walls have one number four bar. |