Permit Number: TD-DEV-0223-00141
Parcel: 10707003R

Address:
1109 W GLENN ST

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.3

Permit Number - TD-DEV-0223-00141
Review Name: DEVELOPMENT PACKAGE REVIEW v.3
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
08/02/2023 Site Engineering APPROVED
08/29/2023 TSMR/PDMR - Engineering APPROVED
08/24/2023 TSMR/PDMR - Traffic Engineering APPROVED No Comments (TRMR is Approved)

David Stiffey

David.Stiffey@tucsonaz.gov
08/29/2023 TSMR/PDMR - Zoning APPROVED
09/07/2023 CDRC Post Review Express PENDING ASSIGNMENT
09/05/2023 Commercial Plumbing REQUIRES RESUBMIT Comment not resolved. If the distance from the rim of the cleanout to the pipe invert is 5-feet, the maximum horizontal distance to the next cleanout opening would be 95-feet. You show four sections of the building sewer that are too long. [Initial comment: The maximum distance between cleanouts shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. Reference: Section 708.1.1, IPC 2018.]
08/04/2023 Fire New Construction REQUIRES RESUBMIT -Per IFC table B105.1(2) fire flow for IIB/14380 square feet, unsprinklered, is 2500 for 2hrs. You have 1500 on the coversheet.
-You have three hydrants which is correct. Just need the fire flow data on the coversheet corrected.
thanks
john.vincent@tucsonaz.gov
5203495581
09/07/2023 NPPO REQUIRES RESUBMIT Please revise the NPPO Plan to closer match the sample plan sent over via email.

If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988
09/07/2023 Site Landscape REQUIRES RESUBMIT Please revise the Commercial Rainwater Harvesting Plan to closer match the sample plan sent over.

If you have any questions about these comments, I can be reached at Matthew.Carlton@tucsonaz.gov or 520-837-4988
08/31/2023 Site Zoning REQUIRES RESUBMIT CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Wyatt Berger
Lead Planner

PROJECT: TWC Tucson
Development Package (2nd Review)
TD-DEV-0223-00141

TRANSMITTAL DATE: August 31, 2023

DUE DATE: August 31, 2023

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This plan has been reviewed for compliance with the Unified Development Code (UDC), Administrative Manual (AM) Section 2-06, and the Technical Standards Manual (TSM).

Per UDC Section 3.3.3.G.5.c, an applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year expiration date is August 31, 2024.

1. COMMENT: 2-06.4.8.B – Provide the abandonment information for the easements proposed to be vacated. A hold will be placed on the Certificate of Occupancy of the proposed building until the abandonment information is provided.

2. COMMENT: 2-06.4.9.H.5.a – This comment was not entirely addressed. The proposed handicapped accessible parking signs conflict with the use of wheel stop curbing. An unobstructed clearance of two and one-half feet is required from the front of the wheel stop to the sidewalk curb. A minimum unobstructed clearance of four feet is still required for the pedestrian circulation path.

3. COMMENT: 2-06.4.9.R – This comment was not entirely addressed. The required pedestrian path along the south wall of the proposed building is required to be a minimum of four feet wide (TSM 7-01.4.3.A).

If you have any questions about this transmittal, please contact me at Wyatt.Berger@tucsonaz.gov or at (520) 837-4951.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: A revised development package as well as a comment response letter. To resubmit, visit the Tucson Development Center Online at https://tdc-online.tucsonaz.gov/#/home. The instructions for resubmittal can be found at https://www.tucsonaz.gov/files/pdsd/website/Resubmittals.pdf.
08/01/2023 CDRC Application Completeness Express REVIEW COMPLETED
08/24/2023 Traffic Engineering Review REVIEW COMPLETED No Comments

David Stiffey

David.Stiffey@tucsonaz.gov