This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.

Permit Reviews

Permit Number - TC-COM-1023-02505
Permit Status: Issued
Permit Description: This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.
Start Date Submittal Complete Date Status  
10/30/2023 COMMERCIAL REVIEW - FULL v.1 11/30/2023 REQUIRES RESUBMIT Review Details
12/22/2023 COMMERCIAL REVIEW - FULL v.2 01/23/2024 REQUIRES RESUBMIT Review Details
07/16/2024 COMMERCIAL REVIEW - FULL v.1 08/16/2024 REQUIRES RESUBMIT Review Details
08/29/2024 COMMERCIAL REVIEW - FULL v.2 10/02/2024 APPROVED Review Details
10/10/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/11/2024 APPROVED Review Details
05/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/22/2024 APPROVED Review Details
03/04/2024 RESTAMP - COMMERCIAL v.1 03/05/2024 APPROVED Review Details
10/02/2024 RESTAMP - COMMERCIAL v.1 10/02/2024 APPROVED Review Details
12/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/18/2024 APPROVED Review Details
01/25/2024 COMMERCIAL REVIEW - FULL v.3 03/04/2024 APPROVED Review Details
12/11/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/18/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-1023-02505
Permit Status: Issued
Permit Description: This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.
Total Outstanding Activity Conditions - 10
Date Name
01/30/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
01/30/2024 Masonry Inspection Report submittal review is required.
01/30/2024 SPECIAL INSPECTION FOR MEDICAL GASES IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
01/30/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-1023-02505
Permit Status: Issued
Permit Description: This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.
Date Description Comments
03/05/2024 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
10/30/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
10/30/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
12/18/2024
05/22/2024 Stair Designs must be submitted and approved prior to...
12/15/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-1023-02505
Permite Description: This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.
Total Outstanding Inspections - 24
Last Inspection Date Description Inspector Results Comments
07/23/2024 COT - HCPL - Plumbing Progress N/A Partial Pass Main drain on South of building B.
10/30/2024 COT - HCBU - Preslab N/A Partial Pass Level One, West half.
02/06/2025 COT - HCPL - Plumbing Roof Drains N/A Partial Pass Level Three, Area B.
06/12/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass East side to large elevator, and small elevator.
04/28/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass 4th Floor, area A, DWV.
11/26/2024 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass Levels One through Four, North wall.
04/17/2025 COT - HCBU - Framing N/A Partial Pass
06/06/2025 COT - HCEL - Electrical Above Ceiling N/A Re-inspection required Partial Inspection for Level Two: Complete low voltage wiring.
02/25/2025 COT - LCEL - Electrical Underground N/A Partial Pass Generator conduits.
01/29/2025 COT - HCBU - Interior Shear Bracing N/A Not Ready wanted Fire wall.
09/24/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass Main duct banks underslab
04/01/2025 COT - HCME - Mechanical Progress N/A Partial Pass 2nd floor HVAC
10/14/2024 COT - LCPL - Yard Water Line N/A Canceled
08/04/2025 COT - HCME - Kitchen Hood N/A Canceled
08/01/2025 COT - HCBU - Building Above Ceiling N/A Partial Pass Level one.
12/04/2024 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Partial Pass 12/3/2024 4th floor monoco fire proofing approved. Pending columns and beams at stairways. RFI on angle bracing for coverage.
07/30/2024 COT - HCEL - Grounding/Bonding N/A Partial Pass 7/30/24: ufer for northwest corner property okay to place concrete
11/21/2025 COT - HCEL - Electrical Final N/A Partial Pass Level Three
12/09/2025 COT - HCPL - Plumbing Final N/A Partial Pass OK for Level Two TCO for all Levels.
07/16/2024 COT - FCON - Sprinkler - Final N/A Not Ready customer did not understand inspection descriptions
12/17/2025 ENGR Engineering Final N/A Partial Pass Okay for Level 4 TCO
12/17/25
Bollards need to be finished/painted per plan. Riprap needs to be placed on slope over 3:1 at NW corner Drainage Structure. WHIA basins At east side of parking lot need to be completed. Fence at West side is being installed now.
All Construction Materials and Equipment will need to be secured inside temporary fencing At SW corner of parking lot adjacent to Basin. Not to go past Bullnoses of curbs. While using reach fork or other equipment during duration of TCO flaggers must assist operator to keep public safe from equipment.
Okay for Level 4 TCO
Schedule this inspection when ready to close out final.
12/16/2025 COT - HCBU - TCO N/A Partial Pass OK for Level Three TCO for Levels 1 and 2.
12/19/2025 COT - HCBU - CofO N/A Partial Pass 12/19/25: OK for Level Four TCO.
11/24/2025 COT - FCON - Fire - Final N/A Partial Pass floors 2-3-4 passed.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-1023-02505
Permit Description: This for the construction of a new Group I-2 Institutional - Condition 2, Type I-B Construction, 4 Story In-Patient Rehabilitation Hospital at 355 N. Wilmot Road, Tucson. This will be for the Building Permit connected with the civil and rezoning of the site for Account No. TD-DEV-0623-00283 being currently reviewed.
Total Completed Inspections - 43
Date Description Inspector Results Comments
07/31/2024 COT - HCEL - Electrical Progress Passed
09/13/2024 COT - HCPL - Plumbing Progress Passed
09/24/2024 COT - HCPL - Sewer Passed
09/24/2024 COT - HCEL - Electrical Underground Passed
10/07/2024 PDSD Heavy Commercial Building Division Pre-Construction Meeting Passed
11/04/2024 COT - HCPL - Rough Soil Passed Balance of Level One.
02/25/2025 COT - HCPL - Plumbing Above Ceiling Passed Level Three, Area A, DWV complete. Area B, scepter for Rooms 312-317. Level One, DWV Room 145. Above ceiling DWV 147.
04/02/2025 COT - HCBU - Preslab Passed
04/02/2025 COT - HCBU - Roof Nailing Passed
04/02/2025 COT - HCPL - Medical Gas Preconstruction Mtg Passed
04/15/2025 COT - HCPL - Plumbing Roof Drains Passed
05/28/2025 COT - HCBU - Excavation/Rebar/Zoning Passed Rebar inspection for the oxygen enclosure slab.
06/03/2025 COT - HCPL - Plumbing Intermediate Passed complete
06/05/2025 COT - HCBU - Exterior Clips/Sheathing Passed
06/16/2025 BULD - Electrical Clearance Passed
07/08/2025 COT - HCBU - Building Progress Passed
07/08/2025 COT - HCBU - Framing Passed
07/21/2025 COT - HCEL - Electrical Above Ceiling Passed
07/21/2025 COT - HCEL - Outdoor Lighting Passed
07/21/2025 COT - LCEL - Electrical Underground Passed
08/04/2025 COT - HCBU - Interior Shear Bracing Passed
08/04/2025 COT - HCBU - Masonry Pregrout Passed
08/04/2025 COT - HCEL - Electrical Intermediate Passed
08/04/2025 COT - HCME - Mechanical Progress Passed
08/04/2025 COT - HCPL - Gas Pressure Test Passed
08/04/2025 COT - LCPL - Yard Water Line Passed
08/04/2025 COT - LCPL - Plumbing Roof Drains Passed
09/17/2025 COT - HCME - Kitchen Hood Passed Complete tie ins to exhaust fans 4,5,&6. Two grease and the other is for the dishwasher. 9/17/2025
09/18/2025 COT - HCPL - Gas Final Passed
10/06/2025 TRSP - ROW - Final/Close-Out Passed
10/10/2025 COT - HCBU - Building Above Ceiling Passed
10/22/2025 COT - HCME - Mechanical Above Ceiling Passed Note: Walls around piping in Soiled hold rooms are not per plans.
10/24/2025 COT - HCME - Mechanical Intermediate Passed
11/21/2025 COT - HCBU - Firewall/Fire Barrier/Firestop Passed
11/21/2025 COT - BULD - SWG Clearance Passed previously inspected
12/05/2025 COT - HCEL - Electrical Final Passed
12/09/2025 COT - HCME - Mechanical Final Passed
12/11/2025 COT - HCPL - Plumbing Final Passed 12/11/25 plumbing complete
12/15/2025 COT - HCPL - Medical Gas/Final Passed
12/15/2025 COT - HCPL - Medical Gas/Test Passed
12/16/2025 COT - FCON - Alarm - Final Passed
12/18/2025 COT - HCBU - Building Final Passed OK for Level Four TCO.
12/19/2025 COT - HCBU - TCO Passed 12/19/25: OK for Level Four TCO.

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
CHLORINATION REPORTS-2025-12-09_V1.PDF DOCUMENTS VIEW
GWG3 TRANS SUB - HAYDEN 4 - 12-3-2024_V1.PDF DOCUMENTS VIEW
APPROVED ATS, MTS, QUICK CONNECT FOR DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
APPROVED GENERATOR FOR DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
APPROVED SHOPS AND CALCS FOR DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
APPROVED STOREFRONTS AND CURTAIN WALL CALCS FOR DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
APPROVED STOREFRONTS AND CURTAIN WALL SHOP DRAWINGS FOR DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-CONS-VOL. 1 - CONSOLIDATED 100 - LIFE SAFETY CIVIL LANDSCAPING STRUCT - ARCH PR-5.082624_V2_V1.PDF DOCUMENTS VIEW
CONS-VOL. 2 - CONSOLIDATED 100 MEPF DRAWINGS TO PR-4R3_V1_V1.PDF DOCUMENTS VIEW
CONS-VOL. 3 - CONSOLIDATED 100 CONSOLIDATED OWNER VENDOR DRAWINGS TO PR-4R3_V1_V1.PDF DOCUMENTS VIEW
AF STEEL - EAST STAIR COMBINED CALCS AND DRAWINGS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-CONS VOL. 1 THRU VOL. 3 CONSOLIDATED 100 PLANS 012524_V3.PDF DOCUMENTS VIEW