Inspection Status: Partial Pass
Inspection History: COT - HCBU - Exterior Clips/Sheathing
| Date |
Description |
Inspector |
Results |
Comments |
| 02/12/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
Levels Two and Three, Framing/Sheathing West Exterior Wall. |
| 02/14/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
2-14-25, partial pass-exterior clip/sheathing on west end level 4. Partial pass-Level 2 hard ceiling soffits. Okay to continue construction at progress areas. Level 1-wall framing verified as per approved plans. Section on southeast quad still needs wall framing inspection. Partial pass-Level 1 main electric room conduits together with elevator shafts 1 & 2 verified-okay to continue with construction at progress areas. |
| 03/07/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Re-inspection required |
3-7-25, called Marco at 1031am and received a response indicating he was a meeting. Waited until 1050 am and left site. Reschedule inspection at your convenience. |
| 03/10/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
3-10-25, screws for west side exterior soffit approved. Okay to continue with construction at progress areas. |
| 04/11/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
East Stair Exterior Sheathing. |
| 05/06/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
3 rd floor lobby, vestibule, West stair, |
| 06/05/2025 |
COT - HCBU - Exterior Clips/Sheathing |
|
Passed |
|
| 11/08/2024 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
North wall. Levels one through three, ok to cover. |
| 11/15/2024 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
11/15/24: North wall exterior from 4th floor to roof parapet okay to cover with dens-gold. |
| 11/26/2024 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
Levels One through Four, North wall. |
| 12/10/2024 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
East extension all Levels. |
| 12/31/2024 |
COT - HCBU - Exterior Clips/Sheathing |
|
Partial Pass |
12-31-24, exterior clips/sheathing on south wall, levels 1-4 verified as per approved plans. Okay to continue with construction. |