Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Permit Number - TC-COM-1023-02505

Inspection Description - COT - HCBU - Framing

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/16/2025 COT - HCBU - Framing Partial Pass Level Three; Ok to one-side.
01/30/2025 COT - HCBU - Framing Canceled
02/06/2025 COT - HCBU - Framing Partial Pass Level One; Area A, shafts and corridors. Sheathing on West wall.
02/12/2025 COT - HCBU - Framing Partial Pass Second Floor Soffits & Ceilings
02/13/2025 COT - HCBU - Framing Partial Pass Level Four, West wall sheathing. Ok to cover.
02/25/2025 COT - HCBU - Framing Partial Pass Level One. Level Two, Ceilings.
03/04/2025 COT - HCBU - Framing Partial Pass West Exterior Soffit
03/14/2025 COT - HCBU - Framing Partial Pass Lvl 2 Ceilings/Soffits
03/25/2025 COT - HCBU - Framing Partial Pass Framing and shafts on level 4.
04/03/2025 COT - HCBU - Framing Partial Pass Outside East. Lvel Four: Shafts.
04/07/2025 COT - HCBU - Framing Partial Pass Exterior East Stair
04/17/2025 COT - HCBU - Framing Partial Pass
04/22/2025 COT - HCBU - Framing Partial Pass st Floor Area B (East) Framing
04/29/2025 COT - HCBU - Framing Partial Pass
05/02/2025 COT - HCBU - Framing Partial Pass Level 4 Stairway Framing.
05/06/2025 COT - HCBU - Framing Partial Pass Level One, Columns at Day room, Level Three, Rooms 310, 310A, 311, 311A and 311B. Level Four, Area A soffits and ceilings.
05/23/2025 COT - HCBU - Framing Partial Pass 4th floor west stairs framing.
05/28/2025 COT - HCBU - Framing Partial Pass 4th floor area B, shower ceiling soffits framing.
06/04/2025 COT - HCBU - Framing Partial Pass Stairwell soffits.
07/08/2025 COT - HCBU - Framing Passed
12/05/2024 COT - HCBU - Framing Partial Pass East end projection.
12/09/2024 COT - HCBU - Framing Partial Pass Partial inspection of Level Two, except grid lines 2-5 from C-D. Looked at Core board, except at Northwest shaft and stairs.
Sheathing at East extension.
12/13/2024 COT - HCBU - Framing Partial Pass 12/13/24: South side of building levels 3 & 4 are properly framed. Okay to proceed with other work.