07/01/2024 | COT - HCPL - Rough Soil | Partial Pass | Storm line is 67% complete. Main catch basins are installed and manhole is poured in place. Remaining connections are 4 each 6" lines for roof drains. Okay to shade and backfill north/ south lateral and 120' of east/west lateral lines. | |
07/02/2024 | COT - HCPL - Rough Soil | Partial Pass | Storm drain, South side, from Roof Drain East to 45 degree turn. | |
07/03/2024 | COT - HCPL - Rough Soil | Partial Pass | Two six inch sub grade drains on South side at West end. | |
07/09/2024 | COT - HCPL - Rough Soil | Partial Pass | South end of main drain. | |
07/15/2024 | COT - HCPL - Rough Soil | Passed | 6" main drain, North side of section B. | |
09/16/2024 | COT - HCPL - Rough Soil | Partial Pass | West half of north main drain. | |
09/16/2024 | COT - HCPL - Rough Soil | Partial Pass | West half of north main drain. | |
09/19/2024 | COT - HCPL - Rough Soil | Partial Pass | West half of South main drain. | |
09/24/2024 | COT - HCPL - Rough Soil | Partial Pass | copper entries in to building | |
09/24/2024 | COT - HCPL - Rough Soil | Passed | ||
09/30/2024 | COT - HCPL - Rough Soil | Canceled | Level One; Women's, men's, and staff restrooms. Sink by TA1 and 4, Drinking fountains. Mop sink. | |
10/03/2024 | COT - HCPL - Rough Soil | Partial Pass | 10/3/24: partial for first 30 feet of main water line north east corner of property | |
10/10/2024 | COT - HCPL - Rough Soil | Not Ready | 10-10-24: Level One, Rooms 157, 158, 160, 164, | |
10/15/2024 | COT - HCPL - Rough Soil | Canceled | ||
10/22/2024 | COT - HCPL - Rough Soil | Partial Pass | Level One, Rooms 103 and 154B. | |
10/28/2024 | COT - HCPL - Rough Soil | Partial Pass | Level One, Kitchen. | |
11/04/2024 | COT - HCPL - Rough Soil | Passed | Balance of Level One. |