Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/28/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
Site concrete turn down wall reinforcement at south west retention basin |
| 11/03/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
Light pole bases. |
| 11/04/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
Kitchen area ACT grid system and mechanical & electrical in ceiling installation. |
| 11/13/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
Grab bars on Levels 2 and 3. |
| 11/19/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
OK for Level Two TCO on Level Three. |
| 12/15/2025 |
COT - HCBU - Building Final |
|
Partial Pass |
Mechanical, electrical, and Med gas rooms on Level One OK for TCO 4. |
| 12/18/2025 |
COT - HCBU - Building Final |
|
Passed |
OK for Level Four TCO. |