Permit: TC-COM-0325-00501
Permit Details
Status:
Fees Paid
Type:
Commercial Building
Address:
980 W IRVINGTON RD
Address NEW:
980 W IRVINGTON RD
Apply Date:
03/14/2025
Applicant:
John Krawietz
Description:
New, ground up construction of a 3-story self storage facility
Permit Reviews
Permit Number - TC-COM-0325-00501
Permit Status: Fees paid
Permit Description: New, ground up construction of a 3-story self storage facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/17/2026 | SPECIAL INSPECTION REVIEW v.1 | N/A | IN REVIEW |
| 02/02/2026 | ADMINISTRATIVE v.1 | 02/02/2026 | REQUIRES RESUBMIT |
| 03/19/2025 | COMMERCIAL REVIEW - FULL v.2 | 04/15/2025 | REQUIRES RESUBMIT |
| 01/06/2026 | COMMERCIAL REVIEW - FULL v.5 | 01/16/2026 | APPROVED |
| 01/30/2026 | COMMERCIAL REVIEW - LIMITED v.2 | 02/02/2026 | APPROVED |
| 12/09/2025 | COMMERCIAL REVIEW - FULL v.4 | 12/31/2025 | REQUIRES RESUBMIT |
| 09/22/2025 | COMMERCIAL REVIEW - FULL v.3 | 10/16/2025 | REQUIRES RESUBMIT |
| 01/21/2026 | COMMERCIAL REVIEW - LIMITED v.1 | 01/21/2026 | REQUIRES RESUBMIT |
| 07/23/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/29/2026 | APPROVED |
| 01/16/2026 | RESTAMP - COMMERCIAL v.1 | 01/21/2026 | APPROVED |
| 03/18/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/18/2025 | REQUIRES RESUBMIT |
| 08/06/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 08/07/2026 | APPROVED |
| 06/22/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/07/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0325-00501
Permit Status: Fees paid
Permit Description: New, ground up construction of a 3-story self storage facility
Total Outstanding Activity Conditions - 19
| Date | Name |
|---|---|
| 01/09/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 11/21/2025 | AIR BALANCING REPORT IS REQUIRED. |
| 11/21/2025 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 11/21/2025 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 11/21/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/21/2025 | COMMISSIONING REPORT IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/21/2025 | Elevator Designs must be submitted and approved prior to ... |
| 11/21/2025 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 11/21/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 11/21/2025 | Post-Installed Anchor Inspection Report is required. |
| 11/21/2025 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 11/21/2025 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
| 12/29/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0325-00501
Permit Status: Fees paid
Permit Description: New, ground up construction of a 3-story self storage facility
| Date | Description | Comments |
|---|---|---|
| 03/18/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/18/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 11/13/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 10/06/2025 | Prior to project being finalized applicant must provide proof of recordation of abandonment of 16' electrical easement. |
Outstanding Inspections
Permit Status: Fees Paid
Permit Number: TC-COM-0325-00501
Permite Description: New, ground up construction of a 3-story self storage facility
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2026 | COT - HCPL - Sewer | N/A | Partial Pass | 3-25-26: verified sewer test at 4psi on a 31' run with a 4" SDR 35 PVC line. Per IPC 306.2.4., a tracer wire for all plastic sewer piping is required. |
| 05/15/2026 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 5-15-26: Roof nailing /reinforcement at metal roof decking verified per S3.1-second floor slab notes 1-6 & S1.1/decking/material note #7 & roof installation, notes #2. Okay for concrete placement at progress areas. |
| 04/07/2026 | COT - HCBU - Preslab | N/A | Partial Pass | 4-7-26: excavation/Reinforcement on 4 interior footings verified per footing schedule F30, F45-G/L 21/ D-L, F60-G/L31/C-D, reinforcement/excavation for remaining exterior footings from G/L 33-West to D and north from G/L H -27 verified per footing schedule F30, F35, F45 and S2.1, details 101. Okay for concrete placement at progress areas. |
| 08/05/2026 | COT - HCBU - Framing | N/A | Partial Pass | Partial pass. 3rd floor framing approved per third party reports. 8/5/2026 |
| 08/05/2026 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | Insulation inspection not required. 8/5/2026 |
| 08/06/2026 | COT - HCME - Mechanical Progress | N/A | Partial Pass | Partial pass. Units hung 1st and 2nd floors. Provide documentation on units for pan requirements along with specs on over flow devices. Re inspection required once duct is in place. 8/6/2026 |
| 04/07/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 4-7-26: 1" domestic verified under test at 126 psi near fire pump together with a 3" underground plumbing drain from sump pump at elevator pit at G/L- C-D/1-9. Okay to backfill approximately 85' of trench using shading materials. |
| 04/07/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 4-7-26: verified 15-1" schedule 40 conduits at sump/elevator shaft, 7-3/4" secondary conduits on west end running north to south for lighting/hvac 2nd floor, and additional conduits consisting of 1" & 3/4" conduits for p1, m1, p2, lp1 at south side of site. Okay to backfill progress areas using shading materials. |
| 08/14/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 8/14/2026 Partial pass. 1st floor both bathrooms, break room, front office and data room approved for in walls and above rough in’s. |
| 08/17/2026 | BULD - Electrical Clearance | N/A | Partial Pass | Partial pass. Clearance to TEP TMPP. 8/17/2026 |