Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
4-1-26: underground plumbing on 1st floor verified under test & per layout on P2.1. Okay to backfill using shading materials. |
| 04/02/2026 |
COT - HCPL - Plumbing Progress |
|
Not Ready |
|
| 04/07/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
4-7-26: 1" domestic verified under test at 126 psi near fire pump together with a 3" underground plumbing drain from sump pump at elevator pit at G/L- C-D/1-9. Okay to backfill approximately 85' of trench using shading materials. |
| 08/07/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
8-7-26: total of 10 roof drains verified under test. 1st floor office/restrooms DWV/domestic verified under test. All in wall plumbing properly secured- make sure roof drains going through levels is not make direct contact with rough metal framing edges. We will check this at finals. Also, if you haven't done so already please submit roof drain RFI to the city for review/approval. Okay to continue construction at progress areas. |