Permit: TC-COM-0325-00501

Parcel: 120052770


Addresses:

980 W IRVINGTON RD

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Preslab  

Date Description Inspector Results Comments
03/25/2026 COT - HCBU - Preslab   Partial Pass 3-25-26: reinforcement for elevator pit slab/sump pit verified per S2.1/detail 110. Okay for concrete placement at progress areas.
04/01/2026 COT - HCBU - Preslab   Partial Pass 4-1-26: excavation/reinforcement on exterior footings at G/L-A/1-32 on east side, A-W at north end and W-27 on west side. Footers verified per S2.0, isolated footing schedule and details 101, 112, 117 & 111 for elevator shaft walls. Okay for concrete placement at progress areas.
04/07/2026 COT - HCBU - Preslab   Partial Pass 4-7-26: excavation/Reinforcement on 4 interior footings verified per footing schedule F30, F45-G/L 21/ D-L, F60-G/L31/C-D, reinforcement/excavation for remaining exterior footings from G/L 33-West to D and north from G/L H -27 verified per footing schedule F30, F35, F45 and S2.1, details 101. Okay for concrete placement at progress areas.
04/13/2026 COT - HCBU - Preslab   Partial Pass 4-13-26: reinforcement/vapor barrier for mat verified per S2.0, detail's 104/110. Okay for concrete placement at own risk-see note below.
Note: verified stack on a total of 9-4" roof drains under test. Plans originally called for 8" roof drains-an RFI was submitted to the city for review.
05/15/2026 COT - HCBU - Preslab   Partial Pass 5-15-26: reinforcement at metal roof decking verified per S3.1-second floor slab notes 1-6 & S1.1/decking/material note #7 & roof installation, notes #2. Okay for concrete placement at progress areas.
06/18/2026 COT - HCBU - Preslab   Partial Pass 6-18-26: reinforcement/preslab at at 3rd floor decking approved-Okay for concrete placement.