Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - HCEL - Electrical Progress |
|
Partial Pass |
4-1-26: verified 9-1" secondary Schedule 40 electrical conduits together with 4-4" conduits for transformer, mdp, panel, lp1, and 10-1" conduits for elevator all at 1st floor. Okay to backfill progress areas. |
| 04/07/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
4-7-26: verified 15-1" schedule 40 conduits at sump/elevator shaft, 7-3/4" secondary conduits on west end running north to south for lighting/hvac 2nd floor, and additional conduits consisting of 1" & 3/4" conduits for p1, m1, p2, lp1 at south side of site. Okay to backfill progress areas using shading materials. |
| 08/06/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
8/6/2026 partial pass. 1st and 2nd floor storage areas inspected. Pending j boxes to be grounded and labeled throughout. Ensure ko seals are installed. Common areas and bathrooms still need to be inspected. |
| 08/14/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
8/14/2026 Partial pass. 1st floor both bathrooms, break room, front office and data room approved for in walls and above rough in’s. |