Permit: T21CM07236
Permit Details
Apply Date:
09/08/2021
Applicant:
Miguel Noriega
Description:
Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
Permit Reviews
Permit Number - T21CM07236
Permit Status: Issued
Permit Description: Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/08/2021 | 3RD PARTY REVIEW - COMMERCIAL | 11/15/2021 | COMPLETED |
| 12/14/2021 | RESUBMITTAL | 08/02/2022 | COMPLETED |
| 01/29/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/02/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM07236
Permit Status: Issued
Permit Description: Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
Total Outstanding Activity Conditions - 11
| Date | Name |
|---|---|
| 01/23/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 01/23/2025 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
| 01/23/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 01/23/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 02/18/2025 | SHOP DRAWINGS REQUIRED FOR STEEL STAIRS |
Conditions
Permit Number - T21CM07236
Permit Status: Issued
Permit Description: Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
| Date | Description | Comments |
|---|---|---|
| 08/01/2022 | Do not issue this building permit until DP21-0005 has been issued. | |
| 11/30/2022 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 01/23/2025 | SHOP DRAWINGS REQUIRED FOR WOOD TRUSSES | |
| 08/01/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. | |
| 01/23/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/18/2025 | SHOP DRAWINGS REQUIRED FOR WOOD I-JOISTS |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM07236
Permite Description: Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
Total Outstanding Inspections - 34
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Roof Drains | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Backwater Valve | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 03/13/2025 | COT - LCEL - Temporary Service | N/A | Not Ready | 3-13-25. Precon meeting with contractor to establish temporary power. Contractor must obtain power from TEP then install panel to specifications outlined in approved plans then Reschedule temporary service inspection. |
| 10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | |
| 11/10/2025 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 11/10/2025 partial pass. Corrections have been made. Okay for concrete placement in footings along with pad. Pending exterior stairway footings. |
| 01/29/2026 | COT - LCBU - Framing | N/A | Partial Pass | Partial pass. Pending intermediate. 1/29/2026 |
| 10/26/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
| 10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
| 03/09/2026 | COT - LCEL - Electrical Progress | N/A | Partial Pass | 3-9-26: verified trench depth at 4' for a 4" Schedule 40 electric conduit for a transformer tie in together with a 2" cox communication conduit running west to east on north side of building. Okay to backfill approximately 340' of open trench. |
| 07/23/2025 | COT - LCPL - Plumbing Progress | N/A | Partial Pass | Interior underground plumbing at sewer and lateral lines. Ok to cover progress areas. |
| 03/25/2026 | COT - FCON - Underground Pressure | N/A | Partial Pass | 0k to burry. They still need a seperate plan and permit for the underground before we can final the underground. |
| 08/12/2026 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Underground Flush | N/A | Not Ready | |
| 08/12/2026 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
| 08/12/2026 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM07236
Permit Description: Proposed Ground Up Multi Family Development, 19 total units. Associated parking and site development
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2025 | BULD - Electrical Clearance | Passed | Approved 100A Temp service panel on pole - TMPP Clearance to TEP is required for the construction power | |
| 03/26/2025 | COT - LCEL - Temporary Service | Passed | Approved 100A Temp service panel on pole - TMPP Clearance to TEP is required for the construction power | |
| 06/05/2025 | COT - LCBU - Stem Wall/Retaining Wall | Passed | Southeast section stem wall at final lift approved. Okay to grout. 6/5/2025 | |
| 07/23/2025 | COT - LCPL - Sewer | Passed | Six inch sewer line connected to main sewer line. | |
| 01/29/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 01/30/2026 | COT - LCBU - Roof Nailing | Passed | ||
| 02/19/2026 | FCON – OH Piping & Hydro | Passed | Approved by will Motto 2/18/2026 |