| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Progress | Not Ready | ||
| 05/11/2026 | COT - LCBU - Building Progress | Partial Pass | ok to proceed on stucco | |
| 08/12/2026 | COT - LCBU - Building Progress | Not Ready | ||
| 09/01/2026 | COT - LCBU - Building Progress | Partial Pass | 9-1-26: MEP progress inspection on unit's 10-firecaulk feeder penetrations at decking & above ceiling, strap mini split feeders, insulate hot pet lines 3/4" and larger, add plastic bushings at sub panels, block block party walls at wall gaps, 8-same notes, cou-le of units on 2nd floor-ground pancake box, putty pack required at party walls when receptacles are within 2' from each other, strap/secure exhausts within 2' of a bend and at 4' intervals thereafter, plastic bushings at panel and insulation of hot pex lines, seal penetrations at top plates, decking and at party walls. | |
| 10/09/2026 | COT - LCBU - Building Progress | Re-inspection required | Here are the notes from today. 10/9/26: Dryers duct cannot be double wall pipe per IMC and manufacturer requirements. Dryers cannot share dryer Duct ( 1st and 2nd floor unit) cannot tie into (3rd and 4th unit). Exhaust fans must be UL listed and shall have appropriate sized duct. Revision required for mechanical modifications. 5-sided gypsum box required at refrigerator boxes . |