Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM03789
Permit Details
Apply Date:
05/29/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
FOUNDATION ONLY FOR FUTURE 10-STORY BLDG
Contractors:
- 3411 BUILDERS INC **APA**
Permit Reviews
Permit Number - T19CM03789
Permit Status: L of c
Permit Description: FOUNDATION ONLY FOR FUTURE 10-STORY BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/21/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 03/05/2020 | COMPLETED |
05/14/2021 | 3RD PARTY REVIEW - REVISION/OTHER | 07/12/2021 | COMPLETED |
05/29/2019 | PLANS OK TO SUBMIT - COMM | 05/29/2019 | COMPLETED |
05/29/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 08/19/2019 | COMPLETED |
08/19/2019 | POST 3RD PARTY REVIEW | 08/19/2019 | COMPLETED |
08/26/2019 | POST 3RD PARTY REVIEW | 12/06/2019 | COMPLETED |
12/06/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 12/06/2019 | COMPLETED |
12/17/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 02/21/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03789
Permit Status: L of c
Permit Description: FOUNDATION ONLY FOR FUTURE 10-STORY BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/29/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM03789
Permit Description: FOUNDATION ONLY FOR FUTURE 10-STORY BLDG
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/13/2020 | SITE - SEWER | JBURGE | Approved | Approved.. Ok to cover progress areas. Two 10” sewer lines from North portion of building to sewer main in 2nd Street. |
10/20/2020 | STEM WALL/RETAINING WALL | JBURGE | Approved | Not ready. Contractor cancelled. |
10/20/2020 | BUILDING PRE-SLAB | JBURGE | Approved | Not ready. Contractor cancelled. |
10/23/2020 | BUILDING - PROGRESS | JBURGE | Approved | Not ready, will reschedule for 26 October. |
10/27/2020 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | Partial. Garage Level, Stairwell C, South wall - top out. Elevators PE #1 & #2 - top out. Generator room North wall - top out. Ok to grout progress areas. |
10/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Partial. Level Roof; Shear walls #6; 7; 8. Ok to set forms and place concrete in progress areas. |
11/19/2020 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Partial. Level #2; Room Units 216; 217; 218 |
05/13/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO/ Room Units electric meters and room panels to be energized: Level #4: 401, 402, 403, 404. 405, 406, 407, 408, 410, 411, 412, 413, 414. 415, 416, 417, 418 Level #5: 501, 502, 503, 504, 505, 506, 507, 508. 510, 511, 512, 513, 514, 515, 516, 517, 518. |
07/27/2021 | NPPO - FINAL | BBENEDON | Approved | APPROVED FOUNDATION PERMIT |
07/27/2021 | SIGN - FINAL | BBENEDON | Approved | APPROVED FOUNDATION PERMIT |
07/27/2021 | LANDSCAPE - FINAL | BBENEDON | Approved | APPROVED FOUNDATION PERMIT |
07/27/2021 | ENGINEERING - FINAL | BBENEDON | Approved | APPROVED FOUNDATION PERMIT |
07/27/2021 | MECHANICAL - FINAL | JBURGE | Approved | |
07/27/2021 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
07/27/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | |
07/27/2021 | SHEET ROCK NAILING | JBURGE | Approved | |
07/27/2021 | FRAMING | JBURGE | Approved | |
07/27/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
07/27/2021 | PLUMBING - FINAL | JBURGE | Approved | |
07/27/2021 | PLUMBING - MD GAS/PRECONST MTG | JBURGE | Approved | |
07/27/2021 | PLUMBING - PRE SLAB | JBURGE | Approved | |
07/27/2021 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | |
07/27/2021 | ELECTRIC - FINAL | JBURGE | Approved | |
07/27/2021 | ELECTRIC - CABLE DROP | JBURGE | Approved | |
07/27/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
07/27/2021 | ELECTRIC - UNDERGROUND | JBURGE | Approved | |
07/27/2021 | ELECTRIC - UFER | JBURGE | Approved | |
07/28/2021 | RIGHT OF WAY - FINAL | Bravin | Approved | no right of way issues |
08/04/2021 | GAS CLEARANCE | JBURGE | Approved | CODE |
08/05/2021 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | Approved Please resubmit for gas clearance. Called in to SW Gas at 0850 hours |
08/27/2021 | BUILDING - FINAL | JBURGE | Approved | . Approved Please close out this permit |
08/27/2021 | FIRE - FINAL | jfordney | Approved | Fire protection inspections included on other permits |
09/01/2021 | ZONING - FINAL | RSALDAT1 | Approved | ZONING WILL BE TRACKED BY T19CM05218 |
09/01/2021 | ZONING PROGRESS | RSALDAT1 | Approved | AP ZONING, ON THIS PERMIT, ZONING WILL BE FOLLOWED ON T19CM05218 |