Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 08/27/2021 |
BUILDING - PROGRESS |
|
Approved |
Approved |
| 08/12/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial: All room units final inspections are complete. Pre-TCO inspections of 11 August write-ups have been corrected. |
| 07/27/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
JBURGE CHANGED INSPECTION FROM A PREVOUS AP TO PA. |
| 10/23/2020 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Not ready, will reschedule for 26 October. |
| 10/22/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial. Electric room equipment pads at 12’ x 12’ and 5’ x 20’. Ok to place concrete in progress areas. |
| 10/20/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial. (01035) Room Units at Level #1; 01; 02; 03; 04. |
| 10/15/2020 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 05/11/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial. Set schedule for Monday 11 May. |