Permit: T19CM03789

Parcel: 12404098A


Addresses:

947 N PARK AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T19CM03789

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
07/27/2021 EXCAVATION/LAYOUT REBAR & ZON Approved
10/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level Roof; Shear walls #6; 7; 8. Ok to set forms and place concrete in progress areas.
09/30/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #8 Mezzanine columns at GL: J/7.8; K/7.8; K/5.6; J/5.6; J/4.2; J/3.2; K3.2; K/2; J.7/1; I.3/2; I.3/1. Ok to place concrete in progress areas.
09/23/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Level #8; pour #1: Shear walls #6; 7; 8 at GL: G-G.2/3-3.9. Ok to set forms a d place concrete.
09/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Level #7; Pour #2: Shear wall #5 at GL:F/3-4. Columns at GL: F.2/4.4; F.4/4; F.4/3; F.7/1; F.7/2; F4/1; F.4/2; E.6/1; E.6/2; D.8/2; D.8/1; B/1; B/2; B/3; D/3; D.9/3.
Ok to place concrete in progress areas.
09/09/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Level #7; Pour #2; section 2: Columns at GL: G/4.4; G.9/4.4; I.2/3; J/3.2; K/3.2; K/2; J.7/1; I.3/1; I.3/2; H.5/2; H.5/1; H.1/2; H 1/1; G.2/2; G.2/1. Shear wall #2 at J/1-2. OK to place concrete in progress areas.
09/02/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #6; Pour #1: Columns at GL: D/4; B/4; B/5; D/5; A/6; D/6; C/8; A/8; D.5/9; E.5/9; F.5/9; F.5/8; F.5/7; E.7/5; E.7/6
Ok to place concrete in progress areas.
Shear wall #1 at GL: E-E.7/8; Shear wall #3 at E/5-6.
08/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Shear Walls #6;7;8 at GL: G-G.2/3-3.9. Shear walls #9; 10; 11 at GL: G.6-H.1/3-3.9. Columns at GL: G/4.4; G.9/4.4; F.7/1. OK to place concrete in progress areas.
08/11/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled will reschedule for 12 August.
08/10/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
08/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #4; pour #1; Columns at GL: G.6/9; G.6/7; G.6/8; H/5.6; H.7/9; I.7/9; J/4.2; J/5.6; J/7.8; J.7/4.2; K/5.6; K/7.8; K/9. Ok to set forms and place concrete.
07/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #2; Columns at GL: E.7/5; E.6/6; F.5/7; F.5/8; F.5/9; E.5/9; D.5/9; A/9. Shear wall #1; at GL: D.9-E.7/8. Ok to place concrete in progress areas.
07/15/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #2; shear walls: Shear wall #3 at GL: E/5-6; Shear wall #5 at GL: F/3-4; Shear wall #12 at GL: E.6/0.9-2. Columns at GL: D.8/1; B/4; B/1; C/8; B/3; D/4; D.9/3; D/6; D/5; B/5; D.9/3; A/8. Ok to set forms and place concrete in progress areas.
06/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Garage Level #2; columns at GL: F.5/5; F.7/2; F.4/3; D/4.1. Ok to set forms and place concrete in progress areas.
06/04/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Garage Level #2; East edge of slab at GL; F.7 - K/.9-2. Transformer area at GL: 7.8-9/F.5-G.6. Ok to place concrete in progress areas.
05/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Garage Level #2 Columns:
(C-2) G/5; (C-2) G.2/2; (C-2) I.3/2; (C-2) I.2/3.9; (C-2) H.2/1; (C-1) I.3/1; (C-3) J/4.2; (C-3) J/3.2; (C-5) H/5; (C-5) H/5.6. Ok to place concrete in progress areas.
05/11/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Exterior walls at 10'3" - 20'6"at GL: A-K/.9-9. Ok to set forms and place concrete.
05/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. (VRI). Shear wall at 10’3” at GL: 9/A-E.5; C-1 column at GL: D/6. Ok to place concrete in progress areas.
04/30/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - AP canceled
04/30/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns (C-2) at GL: B/8.2; B/8.4. F-10 column footing at Gl: D/6. Ok to place concrete in progress areas.
04/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Partial. (VRI) Sump base footing at GL: D-D.8/1-2. Column F11 at GL: D/3; Columns C1 at GL: B/4; B/5. Column C2 at GL: C/8. Shear wall at A/3-5 (approximately 60'). Ok to place concrete in progress areas
04/24/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Cancelled by contractor.
04/23/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Exterior wall at GL: A-E.5/9; A/5-9. Ok to place concrete in progress area.
04/22/2020 EXCAVATION/LAYOUT REBAR & ZON Approved Partial. (VRI). Shear wall #3 at GL: E/5-6; East wall at 10’3”; approximately 55’; GL: East wall/E.6-A. Ok to place concrete in progress areas.
04/21/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection RVI Contractor cancelled.
04/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Double Matt footings with columns at GL: D.8-E/5-6; Columns at GL: B/3 T-1; B/2 T-2; B/.9 T-2; D.9/1.9 T-2. Commercial elevator pit walls at GL: E.6-F/3.9-3. Ok to place concrete in progress areas.
04/17/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled. Will reschedule for 20 April
04/16/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled, will reschedule for 17 April
04/15/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI East wall footings at GL: .9/E/A; A/.9-3; double matted with #12 rebar (top) and #9 rebar (bottom). Four column footings at GL: D.8/9; B/9; B/3; B/2. Elevator pit walls at 5’ at GL: P/1; P/2; P/3. Ok to set forms and place concrete in progress areas.
04/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI (VRI), Shear wall #5; GL: F/3-4.1. Column (C-5) at GL: G/4. Ok to place concrete in progress areas.
04/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI Columns at GL: 2/H.5 (C-2); 2/H.1 (C-2); 2/G.2 (C-2);
2/F.7 (C-2); 2/F.4 (C-2); 3/F.4 (C-2); 3.9/F.4 (C-2); 4/F.2 (C-5). Service Elevator walls North and West.
04/10/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1- Steel reinforcement is okay for concrete for columns located at Line 2 to F.4, line 2 to F.7, line 2 to G.2,line 2 to H.1, line 2 to H.5.
2- Steel reinforcement is okay for concrete for Shear wall 9 up to 10’-3” on line 3 between H to G.6, Shear wall 10 line 8 between 3 to 4, Shear wall 11 line 4 between H to G.8, Shear wall 8 line 3.8 between G to G.2, Shear wall 7 line G between 3 to 3.8, Shear wall 6 line 3 between G to G.2 only.
04/09/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RVI (VRI). Commercial elevator slab and Shear wall #5 at GL: G.6-F.5/3-4. Column C-5 at GL: F.5/5. Ok to place concrete in progress areas.
04/08/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (VRI). Shear wall at GL: 9/F.5-E.7; 12” x 10’3”. Ok to place concrete in progress area.
04/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (VRI). Not ready. Contractor cancelled will reschedule for 8 April.
04/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (VRI). Not ready. Contractor cancelled will reschedule for 8 April.
04/03/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (RVI) Retaining wall and C-5 and C-2 columns all at 11’; GL:
6/C.7-G; E.7/5.9-9. Ok to place concrete in progress areas.
04/02/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footing for Basement wall West at GL: 9/E.5-F. Columns; C1 at GL: 8.5/East wall; C-1 at GL: F.7/East wall; Pop-out on East wall, GL: D.6.
Ok to place concrete in progress areas.
RVI
04/01/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Column C2 at GL: F.5/9. Shear walls: #SW4 at GL: H.7-I.2/8; SW12 at GL: E.6/1-2. Retaining wall at East wall/F.9-E.6. Ok to place concrete in progress areas.
03/31/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Retaining wall at East wall/G.2. Shear wall at GL: I/5.6-5. Columns at GL: 5/G.9; 5/G. Footings at GL: 6/F.5-E.7; 5/E.7; 5/F.5; 9/F.5. Ok to place concrete in progress areas.
03/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns on Grid line one, on grid F.4 and G.2. Column on grid line H and 5.6.
Column on grid line 8 and G6. Column on grid line 8 and F.5.
Retaining wall from G6 to F.5
Service elevator footing.
03/26/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval East shear wall at 10’3” at GL: 9/F.5-G.6. Ok to place concrete in progress area.
03/25/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shear wall at GL: 9/H.7-K, at 10’3”. Ok to place concrete in progress area.
03/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval South exterior wall ok to 10’3". West exterior wall ok from grid line K to grid line I.7 at 10’3”. Column footers ok at 8/G.6 and 8/F.7 sub level.
03/23/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footers at columns along east wall from grid line J thru E ok. Exterior wall, south wall grid line K from grid line 7 thru 3 ok 10’3" from sub level.
03/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns at grid line J/3.2, J/4.2, J/5.6, J/7.8, J.7/4.2, l.3/2, I.2/3, l.2/3.9, J.7/1. 39 feet of south wall at west end moving east from sub up 10 foot ok. West ramp wall along grid line 6 from grid line G to I.2, from sub level up 11 foot ok
03/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footer at Gridline I.2 and 3.9 ok pending S.I. Report.
03/18/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Column footings at Gridline J- 3.2, J - 4.2, J - 7.8, I .3 -2, I.2 -3 OK.
03/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval OK to proceed, pending special inspection reports.
03/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pending special inspection reports.
03/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footers at gridline G-6 to bridling E-8 ok
03/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Perimeter footers Gridline 4.4 W. to Gridline nine and Gridline K to Gridline G .6 OK pending special inspection documentation.
03/11/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Cancel by contractor.
03/10/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Temporary shoring proceeding at north east corner upper level. Footers along south wall at west end proceeding but not complete, provide documentation from special inspections at this area, proceed at own risk.
03/09/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Continuing support at lower level south east section.
03/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
03/05/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Over head crane pad at GL: G-G.6/ 5-6. Only placing first 24" of concrete. Shoring/forms to be adjusted to accept remainder of placement. Ok to place concrete in progress areas.
03/04/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shot-Crete wall prep: Southwest wall, approximately 90’; Southeast wall at approximately 75’.
02/28/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Soil Nails continuing at lower level.
02/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Proceeding with soil nails along north wall third level to midpoint
02/26/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Proceeding with soil nails along east wall.
02/25/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Excavation down to third level proceeding along north and west walls.
02/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Continued insertion of soil nails.
02/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Third level south wall mesh attachment OK
02/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Northwest and Southeast walls; #4 wire mesh for reinforcing walls for shot-Crete.
02/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Northeast and Southeast retaining walls; #4 wire mesh. Ok to shot-Crete progress areas
02/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Wire mesh at second level south wall west side OK
02/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Completion of 11 pylons at east side existing light pole.
02/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Total of eight pylons cored at light pole, pre shock Crete ok south wall east half second level down.
02/11/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Proceeding with pylons at light pole east side, three installed at this time
02/10/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Continuing with soil nails.
02/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Continuing with prep for shock Crete.
02/06/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Soil nails proceeding first row north west wall and east wall north end.
02/05/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Continuing with shock create a long south west corner second level.
02/04/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North wall, first row, soil nails 12 through 25 OK.
01/22/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Subgrade I-beam columns 96 and 98 OK.
01/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caissons and I-beam columns 97, 99, 101, 103, 105, 107, 109, 111, 113, 115 OK.
01/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Caisons p97, p99, p101 ok to pour