Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T19CM03789
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/27/2021 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
10/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level Roof; Shear walls #6; 7; 8. Ok to set forms and place concrete in progress areas. | |
09/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #8 Mezzanine columns at GL: J/7.8; K/7.8; K/5.6; J/5.6; J/4.2; J/3.2; K3.2; K/2; J.7/1; I.3/2; I.3/1. Ok to place concrete in progress areas. | |
09/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | . Partial. Level #8; pour #1: Shear walls #6; 7; 8 at GL: G-G.2/3-3.9. Ok to set forms a d place concrete. | |
09/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | . Partial. Level #7; Pour #2: Shear wall #5 at GL:F/3-4. Columns at GL: F.2/4.4; F.4/4; F.4/3; F.7/1; F.7/2; F4/1; F.4/2; E.6/1; E.6/2; D.8/2; D.8/1; B/1; B/2; B/3; D/3; D.9/3. Ok to place concrete in progress areas. |
|
09/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | . Partial. Level #7; Pour #2; section 2: Columns at GL: G/4.4; G.9/4.4; I.2/3; J/3.2; K/3.2; K/2; J.7/1; I.3/1; I.3/2; H.5/2; H.5/1; H.1/2; H 1/1; G.2/2; G.2/1. Shear wall #2 at J/1-2. OK to place concrete in progress areas. | |
09/02/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #6; Pour #1: Columns at GL: D/4; B/4; B/5; D/5; A/6; D/6; C/8; A/8; D.5/9; E.5/9; F.5/9; F.5/8; F.5/7; E.7/5; E.7/6 Ok to place concrete in progress areas. Shear wall #1 at GL: E-E.7/8; Shear wall #3 at E/5-6. |
|
08/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Shear Walls #6;7;8 at GL: G-G.2/3-3.9. Shear walls #9; 10; 11 at GL: G.6-H.1/3-3.9. Columns at GL: G/4.4; G.9/4.4; F.7/1. OK to place concrete in progress areas. | |
08/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled will reschedule for 12 August. | |
08/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
08/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #4; pour #1; Columns at GL: G.6/9; G.6/7; G.6/8; H/5.6; H.7/9; I.7/9; J/4.2; J/5.6; J/7.8; J.7/4.2; K/5.6; K/7.8; K/9. Ok to set forms and place concrete. | |
07/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #2; Columns at GL: E.7/5; E.6/6; F.5/7; F.5/8; F.5/9; E.5/9; D.5/9; A/9. Shear wall #1; at GL: D.9-E.7/8. Ok to place concrete in progress areas. | |
07/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #2; shear walls: Shear wall #3 at GL: E/5-6; Shear wall #5 at GL: F/3-4; Shear wall #12 at GL: E.6/0.9-2. Columns at GL: D.8/1; B/4; B/1; C/8; B/3; D/4; D.9/3; D/6; D/5; B/5; D.9/3; A/8. Ok to set forms and place concrete in progress areas. | |
06/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Garage Level #2; columns at GL: F.5/5; F.7/2; F.4/3; D/4.1. Ok to set forms and place concrete in progress areas. | |
06/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Garage Level #2; East edge of slab at GL; F.7 - K/.9-2. Transformer area at GL: 7.8-9/F.5-G.6. Ok to place concrete in progress areas. | |
05/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Garage Level #2 Columns: (C-2) G/5; (C-2) G.2/2; (C-2) I.3/2; (C-2) I.2/3.9; (C-2) H.2/1; (C-1) I.3/1; (C-3) J/4.2; (C-3) J/3.2; (C-5) H/5; (C-5) H/5.6. Ok to place concrete in progress areas. |
|
05/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Exterior walls at 10'3" - 20'6"at GL: A-K/.9-9. Ok to set forms and place concrete. | |
05/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. (VRI). Shear wall at 10’3” at GL: 9/A-E.5; C-1 column at GL: D/6. Ok to place concrete in progress areas. | |
04/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
04/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns (C-2) at GL: B/8.2; B/8.4. F-10 column footing at Gl: D/6. Ok to place concrete in progress areas. | |
04/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI Partial. (VRI) Sump base footing at GL: D-D.8/1-2. Column F11 at GL: D/3; Columns C1 at GL: B/4; B/5. Column C2 at GL: C/8. Shear wall at A/3-5 (approximately 60'). Ok to place concrete in progress areas | |
04/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Cancelled by contractor. | |
04/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Exterior wall at GL: A-E.5/9; A/5-9. Ok to place concrete in progress area. | |
04/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Partial. (VRI). Shear wall #3 at GL: E/5-6; East wall at 10’3”; approximately 55’; GL: East wall/E.6-A. Ok to place concrete in progress areas. | |
04/21/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | RVI Contractor cancelled. | |
04/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Double Matt footings with columns at GL: D.8-E/5-6; Columns at GL: B/3 T-1; B/2 T-2; B/.9 T-2; D.9/1.9 T-2. Commercial elevator pit walls at GL: E.6-F/3.9-3. Ok to place concrete in progress areas. | |
04/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Contractor cancelled. Will reschedule for 20 April | |
04/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Contractor cancelled, will reschedule for 17 April | |
04/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI East wall footings at GL: .9/E/A; A/.9-3; double matted with #12 rebar (top) and #9 rebar (bottom). Four column footings at GL: D.8/9; B/9; B/3; B/2. Elevator pit walls at 5’ at GL: P/1; P/2; P/3. Ok to set forms and place concrete in progress areas. | |
04/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI (VRI), Shear wall #5; GL: F/3-4.1. Column (C-5) at GL: G/4. Ok to place concrete in progress areas. | |
04/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI Columns at GL: 2/H.5 (C-2); 2/H.1 (C-2); 2/G.2 (C-2); 2/F.7 (C-2); 2/F.4 (C-2); 3/F.4 (C-2); 3.9/F.4 (C-2); 4/F.2 (C-5). Service Elevator walls North and West. |
|
04/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement is okay for concrete for columns located at Line 2 to F.4, line 2 to F.7, line 2 to G.2,line 2 to H.1, line 2 to H.5. 2- Steel reinforcement is okay for concrete for Shear wall 9 up to 10’-3” on line 3 between H to G.6, Shear wall 10 line 8 between 3 to 4, Shear wall 11 line 4 between H to G.8, Shear wall 8 line 3.8 between G to G.2, Shear wall 7 line G between 3 to 3.8, Shear wall 6 line 3 between G to G.2 only. |
|
04/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RVI (VRI). Commercial elevator slab and Shear wall #5 at GL: G.6-F.5/3-4. Column C-5 at GL: F.5/5. Ok to place concrete in progress areas. | |
04/08/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | (VRI). Shear wall at GL: 9/F.5-E.7; 12” x 10’3”. Ok to place concrete in progress area. | |
04/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | (VRI). Not ready. Contractor cancelled will reschedule for 8 April. | |
04/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | (VRI). Not ready. Contractor cancelled will reschedule for 8 April. | |
04/03/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | (RVI) Retaining wall and C-5 and C-2 columns all at 11’; GL: 6/C.7-G; E.7/5.9-9. Ok to place concrete in progress areas. |
|
04/02/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footing for Basement wall West at GL: 9/E.5-F. Columns; C1 at GL: 8.5/East wall; C-1 at GL: F.7/East wall; Pop-out on East wall, GL: D.6. Ok to place concrete in progress areas. RVI |
|
04/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Column C2 at GL: F.5/9. Shear walls: #SW4 at GL: H.7-I.2/8; SW12 at GL: E.6/1-2. Retaining wall at East wall/F.9-E.6. Ok to place concrete in progress areas. | |
03/31/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Retaining wall at East wall/G.2. Shear wall at GL: I/5.6-5. Columns at GL: 5/G.9; 5/G. Footings at GL: 6/F.5-E.7; 5/E.7; 5/F.5; 9/F.5. Ok to place concrete in progress areas. | |
03/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Columns on Grid line one, on grid F.4 and G.2. Column on grid line H and 5.6. Column on grid line 8 and G6. Column on grid line 8 and F.5. Retaining wall from G6 to F.5 Service elevator footing. |
|
03/26/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | East shear wall at 10’3” at GL: 9/F.5-G.6. Ok to place concrete in progress area. | |
03/25/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Shear wall at GL: 9/H.7-K, at 10’3”. Ok to place concrete in progress area. | |
03/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | South exterior wall ok to 10’3". West exterior wall ok from grid line K to grid line I.7 at 10’3”. Column footers ok at 8/G.6 and 8/F.7 sub level. | |
03/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footers at columns along east wall from grid line J thru E ok. Exterior wall, south wall grid line K from grid line 7 thru 3 ok 10’3" from sub level. | |
03/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Columns at grid line J/3.2, J/4.2, J/5.6, J/7.8, J.7/4.2, l.3/2, I.2/3, l.2/3.9, J.7/1. 39 feet of south wall at west end moving east from sub up 10 foot ok. West ramp wall along grid line 6 from grid line G to I.2, from sub level up 11 foot ok | |
03/19/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footer at Gridline I.2 and 3.9 ok pending S.I. Report. | |
03/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Column footings at Gridline J- 3.2, J - 4.2, J - 7.8, I .3 -2, I.2 -3 OK. | |
03/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK to proceed, pending special inspection reports. | |
03/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Pending special inspection reports. | |
03/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footers at gridline G-6 to bridling E-8 ok | |
03/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Perimeter footers Gridline 4.4 W. to Gridline nine and Gridline K to Gridline G .6 OK pending special inspection documentation. | |
03/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Cancel by contractor. | |
03/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Temporary shoring proceeding at north east corner upper level. Footers along south wall at west end proceeding but not complete, provide documentation from special inspections at this area, proceed at own risk. | |
03/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Continuing support at lower level south east section. | |
03/06/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
03/05/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Over head crane pad at GL: G-G.6/ 5-6. Only placing first 24" of concrete. Shoring/forms to be adjusted to accept remainder of placement. Ok to place concrete in progress areas. | |
03/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Shot-Crete wall prep: Southwest wall, approximately 90’; Southeast wall at approximately 75’. | |
02/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Soil Nails continuing at lower level. | |
02/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Proceeding with soil nails along north wall third level to midpoint | |
02/26/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Proceeding with soil nails along east wall. | |
02/25/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Excavation down to third level proceeding along north and west walls. | |
02/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Continued insertion of soil nails. | |
02/21/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Third level south wall mesh attachment OK | |
02/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Northwest and Southeast walls; #4 wire mesh for reinforcing walls for shot-Crete. | |
02/19/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Northeast and Southeast retaining walls; #4 wire mesh. Ok to shot-Crete progress areas | |
02/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Wire mesh at second level south wall west side OK | |
02/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Completion of 11 pylons at east side existing light pole. | |
02/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Total of eight pylons cored at light pole, pre shock Crete ok south wall east half second level down. | |
02/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Proceeding with pylons at light pole east side, three installed at this time | |
02/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Continuing with soil nails. | |
02/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Continuing with prep for shock Crete. | |
02/06/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Soil nails proceeding first row north west wall and east wall north end. | |
02/05/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Continuing with shock create a long south west corner second level. | |
02/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | North wall, first row, soil nails 12 through 25 OK. | |
01/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Subgrade I-beam columns 96 and 98 OK. | |
01/21/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Caissons and I-beam columns 97, 99, 101, 103, 105, 107, 109, 111, 113, 115 OK. | |
01/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Caisons p97, p99, p101 ok to pour |