Permit: T19CM03789

Parcel: 12404098A


Addresses:

947 N PARK AV

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
07/27/2021 BUILDING PRE-SLAB Approved
10/20/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor cancelled.
10/17/2020 BUILDING PRE-SLAB Partial Approval Partial. Roof level at GL; G-K/0.09-9. Post Tension Cable System. Ok to place concrete in progress areas.

Please charge 3411 Construction $165.00 for after hours inspection on this date (APA account).
10/15/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor cancelled.
10/06/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #8 Mezzanine; Pour #2 at. GL: A-H.5/0.09-9. Ok to place concrete in progress areas.
09/29/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #8 Mezzanine at GL: H.5-K/0.9-9; Pour #1. Ok to place concrete in progress areas.
09/24/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #8; Pour #2; Post Tension Cable System at GL: A-G/0.9-9. Shear walls #9; 10; 11 at GL: G.6-H.1/3-4. Ok to place concrete in progress areas.
09/22/2020 BUILDING PRE-SLAB Partial Approval
09/21/2020 BUILDING PRE-SLAB Partial Approval Post tension inspection on Level 8, Pour one, south side.

After hours inspection on 19 September 20. Please charge 3411 Construction (APA ) $165.00 for inspection performed.
09/12/2020 BUILDING PRE-SLAB Partial Approval Partial. Level 7; Post Tension Cable System at GL: A-G/0.09-9. OK to place concrete in progress areas. After hours inspection 12 September 20. Please charge 3411 Construction (APA ) $165.00 for inspection performed.
09/10/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #7; Shear walls #6, 7; 8 at GL: G-G.2/3-4; Shear Walls #9; 10; 11 at GL: G.6-H.1/3-4. Ok to place concrete in progress areas.
09/04/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #7; Pour #1; Section #1 at GL: G-K/0.09-9. Ok to place concrete in slab area.
08/31/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #6; Pour #2; Section #1. Ok to place concrete in slab.
08/25/2020 BUILDING PRE-SLAB Partial Approval Partial. Post Tension Cable System at Level #6; Section #4; Pour #1 at GL: G-K/.09-9. Ok to place concrete in progress area.
08/12/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #5; Post Tension Cable System at GL: G-K/0.09-4.2. Ok to place concrete in progress areas.
08/06/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #4; pour #2 slab at GL:A-G/0.9-9. Ok to place concrete in slab.
07/31/2020 BUILDING PRE-SLAB Partial Approval Partial. Parking garage Level #1; CMU walls at 0”-48” at GL: J-K/7.8-8; G-H/3.5-4.1; A-C/3-2.8; A-B/2-0. Ok to place grout in progress areas.
07/25/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #3; pour #2 at GL: A-F.7/0.9-9. OK to place concrete in progress areas.
07/08/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2; Pour #2 at GL: G-K/0.9-9. Ok to place concrete in progress areas.
07/06/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #1; columns at GL: 9/D.5; 9/E.5. Ok to set forms and place concrete in progress areas.
07/02/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2; Double mat rebar reinforced slab at GL: G.6-I.2/8-9. Ok to place concrete in progress areas.
06/27/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2; Post Tension Cable system at GL: D.9 - I.3/3.9 - 8.1. Columns at GL: A/6; D/3; D.8/2.
06/17/2020 BUILDING PRE-SLAB Partial Approval Partial. Slab at GL: G.6 - I.2/7.8 - 9; 9-2/I.7 K. Ok to place concrete in progress areas.
06/16/2020 BUILDING PRE-SLAB Partial Approval . Partial. Garage Level #2; Columns at GL: B/5; D/6; F.5/8; F.5/6; F.5/4; F.4/1; F.7/1; D.8/.9. Ok to set forms and place concrete.
06/15/2020 BUILDING PRE-SLAB Partial Approval Partial. Garage Level ,#2, slab at GL: A-D/.9-9. Ok to place concrete in progress areas.

After hours inspection at 8:00 am - 9:30 am. Please charge 3411 Construction APA $247.50 for inspection performed.
06/12/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor will reschedule for after hours inspection on 13 June.
06/11/2020 BUILDING PRE-SLAB Partial Approval Partial. Garage Level #2; Edge areas at GL: A-G/.9-2; 3-4/A-C. Ok to place concrete in progress areas.
06/05/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #1; GL: G-K/.9-9. Ok to place concrete in progress areas. Double matted rebar reinforced
05/27/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2; parking garage ramp at GL: H-E.7/5.9-9; A-E.7/5.9-8.1. Ok to place concrete in progress areas.
05/16/2020 BUILDING PRE-SLAB Partial Approval Partial. Garage Level #2; double matted rear reinforced slab at GL,: A-F.5/0.9-9. Ok to place concrete in progress area.
After hours inspection; please charge 3411 Construction $165.00 for inspection performed on 16 May 20.
05/15/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Corrections need to be completed. Request an after hours inspection for 16 May at 0900 hours.
05/11/2020 BUILDING PRE-SLAB Partial Approval Partial. Deck for B2 at GL: G.9/9-6; K/6-9. B1 slab at 5-9/A-E.7. Ok to place concrete in progress areas.
05/08/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor cancelled to be rescheduled 9 May as an after hours inspection at 0900 hours.
05/07/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor cancelled will reschedule for 8 May
05/06/2020 BUILDING PRE-SLAB Not ready for Inspection
05/05/2020 BUILDING PRE-SLAB Partial Approval Partial. Garage Level #1; North and Northeast Sections: GL: A-F/.9-6.
Ok to place concrete in progress areas.
05/04/2020 BUILDING PRE-SLAB Not ready for Inspection RVI Not ready. Contractor cancelled.
04/30/2020 BUILDING PRE-SLAB Cancelled Not ready. Contractor cancelled.
04/29/2020 BUILDING PRE-SLAB Partial Approval RVI Partial. (VRI). Concrete shear wall; 60’x10’”x12” at GL: A/5-8.1. Columns; 6 each C-2 columns at GL: D/3; D/4; D/5; D.9/3; D.8/2; D.9/4.
04/24/2020 BUILDING PRE-SLAB Cancelled Cancelled by contractor.
04/23/2020 BUILDING PRE-SLAB Partial Approval Parking garage ramp and level #1 at GL: A/.9-3; 5.9-9/E.7-K; F.7-K/1-6. Ok to place concrete in progress areas.