Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T19CM03789

Parcel: 12404098A


Addresses:

947 N PARK AV


Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Permit Number - T19CM03789

Inspection Description - REINFORCED MASONRY PRE-GROUT

Inspection Status - Approved

Date Description Inspector Results Comments
07/27/2021 REINFORCED MASONRY PRE-GROUT Approved
10/27/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Garage Level, Stairwell C, South wall - top out. Elevators PE #1 & #2 - top out. Generator room North wall - top out. Ok to grout progress areas.
10/19/2020 REINFORCED MASONRY PRE-GROUT Cancelled Canceled by contractor.
10/15/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Garage Levels; Elevator B at 5’4”-10’; Retail elevator at 0’-9’4”; Service Elevator at 0’-4’; Stairwell A at 0’-4’; Storage at 0’-4’; Stairwell C at 4’-8’. Ok to place grout in progress areas.
10/08/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Level #1; West wall topped out; trash room North and South walls topped out. Ok to place grout in progress areas.
10/07/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; Trash rooms, pump room North and South walls at 12’-16’; West walls at 8’-12’ (Lintels placed at 8’4”. Ok to place grout in progress areas.
10/05/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Level #1; Pump Room CMU walls: East and West at 4'-8'; North and South at 12'-16'. Ok to place grout in progress areas.
10/01/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Trash room North wall at 8’-12’; pump room walls at 4’-10’. Ok to grout progress areas.
09/30/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; Trash rooms; West walls. Top out, Ok to grout progress areas.
09/29/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 0’-4’ in trash room; walls at GL: F-E/5, topped out; Generator Room walls GL: 5-6 (topped out).
09/28/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection
09/25/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
09/24/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1, CMU Walls at GL: D.5/5-6 at 4’-10’; E/5-6 at 4’-10’;5/E-E.6 at 4’-10’; 8.5/F.4-G T 12’-16’. Ok to place concrete in progress areas.
09/22/2020 REINFORCED MASONRY PRE-GROUT Partial Approval
09/21/2020 REINFORCED MASONRY PRE-GROUT Partial Approval 01020. Partial. CMU walls at GL: F.5/5-8.5 (top out); 9/A-E.6 (8’-12’); E.9-F.1/ 5-5.5; E.1/5.2-5.9 (0’-4’). Ok to grout progress areas.
09/17/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Gridlines F.5 to 5, 2nd lift, 4 to 8 feet. Gridlines F to 5 2nd lift, 4 to 8 feet. Gridlines 6 to E7 thru D, top out.
09/15/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: 9/A-B (0’-4’); 8/A-B (0’-4’); E.3/9-8 (top out); F.2/8-9 (top out); 5/E-A (top out); 6/A-B (top out). Ok to place concrete in progress areas.
09/09/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: F/9-8 at 18' top out; 5/A-E at 12'-16'; 6/A-E at 12'-16'; A/8-9 at 0'-4'; E.7/8-9 at 4'-8'; E.7/6-8 top out.
Ok to grout progress areas.
09/03/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at GL: F.2/5-9 at 16’-18’4”; E.7/6-8 at 8’-12’. Ok to grout progress areas.
09/01/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at. GL: Training Room at 0’-4’; CMU wall at F/6-7 at 0’- 4’; Electric Main room at 8’-12’; CMU wall at GL: A-F/5. Ok to grout progress areas.
08/28/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; Room 117; walls at 0’-4’; Main electric room at4’-9’4”; Generator Room at 4’-9’4”; Garage entry at 0’-4’. Ok to place grout in progress areas.
08/27/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 4’-8’, GL: 4.9-5/A-F.2; 6-6.1/A-F; 8-8.1/A-B.7. Ok to place concrete in progress areas.
08/26/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/25/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1 at GL: E.7/9-8 (0’-4’); E.7/8-6 (0’-4’); 6/A-E.7 (0’-4’); 6/A-F top out at 18’. Ok to place grout in progress areas.

Drop to add an attachment
AttachmentsPartial. Level #1 at GL: E.7/9-8 (0’-4’); E.7/8-6 (0’-4’); 6/A-E.7 (0’-4’); 6/A-F top out at 18’. Ok to place grout in progress areas
08/21/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/20/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/19/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/18/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Inspection performed on 17 August.
08/17/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Shear Walls #6;7;8 at GL: G-G.2/3-3.9. Shear walls #9; 10; 11 at GL: G.6-H.1/3-3.9. Columns at GL: G/4.4; G.9/4.4; F.7/1. OK to place concrete in progress areas.
08/12/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. CMU walls at 8’-12’ at GL: F-F.4/0.9-4.2. Ok to place grout in the progress areas.
08/11/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/11/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; Office area; CMU walls at 4’-8’ at GL: 4-4.1/A-F.5; .09-4.1/F-F.4; 4-4.5/F.4-F.5. (Re-inspection). Ok to place grout in progress areas.
08/10/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection NOT READY PER INSPECTOR VIA PHONE
08/07/2020 REINFORCED MASONRY PRE-GROUT Not ready for Inspection Not ready. Contractor cancelled.
08/06/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; CMU Office walls at 0”-48” at,GL: E-F.6/4-4.1. Ok to place grout in progress areas.
08/05/2020 REINFORCED MASONRY PRE-GROUT Partial Approval Partial. Level #1; CMU walls at 0”-48”: GL: F-F.4/0.9-0.4. Ok to place grout in progress areas.
07/31/2020 REINFORCED MASONRY PRE-GROUT Partial Approval