Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
7401 S WILMOT RD
Address NEW:
7401 S WILMOT RD
Apply Date:
10/24/2018
Applicant:
TARVER JONES
Description:
NEW MICRO HOSPITAL
Contractors:
  • ADOLFSON AND PETERSON CONSTRUCTION *C

Permit Reviews

Permit Number - T18CM08485
Permit Status: C of o
Permit Description: NEW MICRO HOSPITAL
Start Date Submittal Complete Date Status  
02/28/2019 RESUBMITTAL 05/01/2019 COMPLETED Review Details
05/01/2019 RESUBMITTAL 05/20/2019 COMPLETED Review Details
10/24/2018 PLANS OK TO SUBMIT - COMM 10/24/2018 COMPLETED Review Details
10/24/2018 COMMERCIAL - NEW 12/20/2018 COMPLETED Review Details
12/21/2018 RESUBMITTAL 02/28/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM08485
Permit Status: C of o
Permit Description: NEW MICRO HOSPITAL
Total Outstanding Activity Conditions - 1
Date Name
10/24/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM08485
Permit Description: NEW MICRO HOSPITAL
Total Completed Inspections - 56
Date Description Inspector Results Comments
07/19/2019 PLUMBING - ROUGH, SOIL AKEINSORGE Approved Area A, ok to backfill. Also all corrections in Area B from inspection on 07/12/19 have been done and are acceptable.
THIS WAS A SAME DAY INSPECTION. $165 FEE HAS BEEN ASSESSED, BUT NOT YET PAID.
08/14/2019 ELECTRIC - UFER AKLEINSORGE Approved 20’ of copper #4 tied to thickened footing on east side of building in a Area B
10/02/2019 BUILDING PRE-SLAB DMUNIZ Approved ok for concrete placement around steel columns for area A.
10/04/2019 PLUMBING - YARD WTR LINE/TEST DMUNIZ Approved Pressure test for 2-3" copper risers ok.
11/12/2019 PLUMBING - PRE SLAB TVALENCIA Approved 1- Water service piping from Riser room to backflow preventers is okay to cover.
11/13/2019 PLUMBING - ROOF DRAINS DMUNIZ Approved 9 sets of Primary and Secondary Roof drains under test and Approved.
11/18/2019 PLUMBING - SEWER HCS CONNECT CTREVIL Approved DO NOT FINAL SEWER CONNECTION UNTIL RWRD FEES HAVE BEEN PAID.
11/21/2019 SITE - SEWER DMUNIZ Approved Inspection for continuation of Sewer from first clean-out to second Clean out and beyond 40’ Tracer installed and clean fill provided ok to backfill.
11/22/2019 PLUMBING - ABOVE CEILING DMUNIZ Approved cast iron Vent system for Area B under test and Approved, stopped inspection at GL J.0.
12/02/2019 EXCAVATION/LAYOUT REBAR & ZON TVALENCIA Approved 1- Steel reinforcement is okay for concrete in X-Ray and CT room only.
12/04/2019 ROOF NAILING DMUNIZ Approved Exterior Ramada roof decking ok for West, & South entrance.
12/11/2019 MECHANICAL - PROGRESS DMUNIZ Approved Inspection for Hi and Low Pressure Ductwork in Area B multiple corrections disclosed to contractor, will call in inspection for above ceiling once completed.
12/18/2019 ELECTRIC - UNDERGROUND DMUNIZ Approved Electrical Conduits for 6 of 8 Exterior light poles ok to shade, tape & backfill.
12/18/2019 SHEET ROCK NAILING DMUNIZ Approved progress Area B.
12/18/2019 EXT METAL CLIPS/EXT SHEATHING DMUNIZ Approved Exterior Sheathing front entry.
12/20/2019 PLUMBING - MEDICAL GAS/TEST DMUNIZ Approved Med Gas Area A & B.
12/23/2019 MECHANICAL - INTERMEDIATE DMUNIZ Approved Area A ok to test and insulate ducts.
12/23/2019 PLUMBING - INTERMEDIATE DMUNIZ Approved no inspection done at this time.
12/23/2019 ELECTRIC - ABOVE CEILING DMUNIZ Approved North East Electrical in ceiling ok.
12/23/2019 FIREWALL/FIREBARRIER/FIRESTOP DMUNIZ Approved area B Top of Fire assemblies ok.
12/23/2019 STUCCO MESH DMUNIZ Approved
12/23/2019 FRAMING DMUNIZ Approved no inspection at this time.
12/27/2019 ELECTRIC - INTERMEDIATE DMUNIZ Approved Area A CT, X-Ray, and exam rooms Electrical in walls ok.
01/06/2020 PLUMBING - GAS PRESSURE TEST DMUNIZ Approved Gas Pressure test for 2" Line from Exterior to location of 2 Water Heaters ok.
02/05/2020 TEP CLEARANCE - PM DMUNIZ Approved CODE ECO
02/07/2020 BUILDING - TEMP POWER FOR TEST DMUNIZ Approved
02/07/2020 ELECTRIC - TEMPORARY SERVICE DMUNIZ Approved
02/07/2020 PLUMBING - MD GAS/PRECONST MTG DMUNIZ Approved
02/28/2020 PLUMBING - BACK WATER VALVE DMUNIZ Approved
02/28/2020 ELECTRIC - CABLE DROP DMUNIZ Approved
02/28/2020 ELECTRIC - SERVICE UPGRADE DMUNIZ Approved
03/03/2020 U VALUE FOR WINDOW DMUNIZ Approved U value details per plan inspected and Approved.
03/05/2020 PLUMBING - PROGRESS DMUNIZ Approved
03/05/2020 ELECTRIC - OUTDOOR LIGHTING DMUNIZ Approved
03/05/2020 REINFORCED MASONRY PRE-GROUT DMUNIZ Approved
03/05/2020 STEM WALL/RETAINING WALL DMUNIZ Approved
03/24/2020 OUTDOOR LIGHTING FINAL DMUNIZ Approved
04/03/2020 PLUMBING - GAS PRESS TEST FNL TVALENCIA Approved Clear gas meter
04/03/2020 MECHANICAL - ABOVE CEILING TVALENCIA Approved
04/03/2020 BUILDING ABOVE CEILING TVALENCIA Approved
04/06/2020 GAS CLEARANCE TVALENCIA Approved CODE
04/16/2020 BUILDING - PROGRESS TTREMBLAK Approved RVI
04/23/2020 PLUMBING - MEDICAL GAS/FINAL TTREMBULAK Approved RVI Cancelled by contractor. Will reschedule after 3rd party inspection
05/04/2020 ZONING - FINAL RLEDONNE Approved OK to approve per Steve shields Land split has been completed.
05/08/2020 ELECTRIC - FINAL DMUNIZ Approved
05/12/2020 LANDSCAPE - FINAL RLEDONNE Approved
05/12/2020 SIGN - FINAL RLEDONNE Approved
05/12/2020 NPPO - FINAL RLEDONNE Approved
05/13/2020 ENGINEERING - FINAL RLEDONNE Approved
05/15/2020 PLUMBING - FINAL DMUNIZ Approved
05/20/2020 FIRE SPKLR - FINAL jvincent Approved
06/05/2020 MECHANICAL - FINAL DMUNIZ Approved
06/05/2020 RIGHT OF WAY - FINAL BMONG Approved ALL WORK IN THE ROW IS WITHIN SPECIFCATIONS
06/09/2020 BUILDING - FINAL JG3 Approved
06/09/2020 FIRE - FINAL jvincent Approved
06/09/2020 FIRE - ALARM FINAL jvincent Approved