Permit: T18CM08485

Parcel: 141366820


Addresses:

7401 S WILMOT RD

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
02/07/2020 EXCAVATION/LAYOUT REBAR & ZON Approved
01/23/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Re bar placement for generator & trash enclosure ok for concrete placement.
01/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
01/15/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled via phone call.
01/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval case ons for light poles ok for concrete placement.
01/09/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Inspection cancel by contractor
01/08/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Generator footing ok for concrete placement, stem wall verticals in place.
12/02/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1- Steel reinforcement is okay for concrete in X-Ray and CT room only.
11/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1- Steel reinforcement for trash enclosure is okay.
11/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Steel reinforcement for front entrance vestibule (C.0-D.0/3.8-4.6) and front Exterior column block outs (A.0-B.0/4.1-4.3). Ok for concrete placement, third party inspection Approved as well.
10/17/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Yard storage and Riser room ok for concrete placement, third party onsite for special inspection and Approved.
10/08/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pads on Roof deck steel in place, ok for concrete placement.
09/30/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor rescheduled upon arrival
09/27/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stem wall/ steel column surround NE corner ok for concrete placement. Third party inspection Approved.
08/21/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Area A: monolithic pour between Grids D to J/1 to 7, excluding Rooms 135, 136, 137, and 140
07/15/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Inspected epoxy anchor bolts for footings (RFI #8) at the following locations: Grids P.0/3.0, M.0/3.0, P.0/4.2, K.0/3.0, F.0/2.0, F.0/6.0, G.0/7.0 and H.0/7.0, special inspection was preformed by Speedie and Associates during the placement of anchor bolts
06/27/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection work incomplete upon arrival.
06/25/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval completion Of column footings (F.0/1.8-2.0, A.0/4.1, A.0/4.3, B.0/4.2) Approved and ok to pour.
06/24/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval All interior column footings and exterior perimeter column footings for south and west side of building, ok for concrete placement