Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T18CM08485
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
01/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Re bar placement for generator & trash enclosure ok for concrete placement. | |
01/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
01/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Contractor cancelled via phone call. | |
01/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | case ons for light poles ok for concrete placement. | |
01/09/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Inspection cancel by contractor | |
01/08/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Generator footing ok for concrete placement, stem wall verticals in place. | |
12/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement is okay for concrete in X-Ray and CT room only. | |
11/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement for trash enclosure is okay. | |
11/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Steel reinforcement for front entrance vestibule (C.0-D.0/3.8-4.6) and front Exterior column block outs (A.0-B.0/4.1-4.3). Ok for concrete placement, third party inspection Approved as well. | |
10/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Yard storage and Riser room ok for concrete placement, third party onsite for special inspection and Approved. | |
10/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Pads on Roof deck steel in place, ok for concrete placement. | |
09/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Contractor rescheduled upon arrival | |
09/27/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Stem wall/ steel column surround NE corner ok for concrete placement. Third party inspection Approved. | |
08/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Area A: monolithic pour between Grids D to J/1 to 7, excluding Rooms 135, 136, 137, and 140 | |
07/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Inspected epoxy anchor bolts for footings (RFI #8) at the following locations: Grids P.0/3.0, M.0/3.0, P.0/4.2, K.0/3.0, F.0/2.0, F.0/6.0, G.0/7.0 and H.0/7.0, special inspection was preformed by Speedie and Associates during the placement of anchor bolts | |
06/27/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | work incomplete upon arrival. | |
06/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | completion Of column footings (F.0/1.8-2.0, A.0/4.1, A.0/4.3, B.0/4.2) Approved and ok to pour. | |
06/24/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | All interior column footings and exterior perimeter column footings for south and west side of building, ok for concrete placement |