Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 02/07/2020 |
BUILDING PRE-SLAB |
|
Approved |
|
| 10/02/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
ok for concrete placement around steel columns for area A. |
| 10/01/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
1- Work is incomplete |
| 09/26/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Area B ok for concrete placement for bulkhead enclosures for steel columns. |
| 09/17/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Bolting of steel columns to footers from Grid Line K.0 to P.0. Ok for compact and grout. |
| 08/21/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Area A: monolithic pour between Grids D to J/1 to 7, excluding Rooms 135, 136, 137, and 140 |
| 08/14/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Area B, monolithic pour with footings, excluding Rooms 306, 313, and 331, ok for concrete placement |
| 08/13/2019 |
BUILDING PRE-SLAB |
|
Cancelled |
Canceled by contractor, will recall when ready |