Permit: T18CM08485

Parcel: 141366820


Addresses:

7401 S WILMOT RD

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
02/07/2020 FRAMING Approved
01/13/2020 FRAMING Partial Approval framing for water fountain coolers ok.
12/23/2019 FRAMING Partial Approval no inspection at this time.
12/11/2019 FRAMING Partial Approval Area A Imaging rooms ok.
11/27/2019 FRAMING Partial Approval South entry Portal Frame ok.
10/16/2019 FRAMING Partial Approval Interior Frame from GL-E.9-H.0. (Except CT an X-Ray room).
10/14/2019 FRAMING Partial Approval No inspection done today.
10/10/2019 FRAMING Cancelled Canceled on site.
10/04/2019 FRAMING Partial Approval Interior frame for GL, K.0-J.3.
10/03/2019 FRAMING Partial Approval inspection rescheduled.
10/02/2019 FRAMING Partial Approval interior frame from Grid Line L.0-k.0. Exterior top of frame for previous exterior inspection
09/30/2019 FRAMING Not ready for Inspection Contractor rescheduled upon arrival
09/25/2019 FRAMING Partial Approval framing ok for Area B, GL- (P.0-L.0). Note: Gave ok for Contractor to Sheetrock one side of Approved framing 4’ from roof deck for MEP Penetrations for Fire rated assemblies.
09/24/2019 FRAMING Not ready for Inspection 1- Contractor called and cancelled the inspection request.