Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 03/05/2020 |
ELECTRIC - INTERMEDIATE |
|
Approved |
|
| 02/28/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Electrical Conduits in CMU wall for generator inspected. |
| 02/21/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Line termination to RTU1 inspected and approved. |
| 02/19/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Line Termination for RTU’s #2 & 3 Inspected. |
| 02/05/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Inspection of 1600AMP 480/277V SES Note: plans call for 5 Parallel #600KCMIL CU Conductors, Contractor substituted with 5- #750KCMIL AL Conductors. Inspection from SES to MSA And to 4 AutomaticTransferSwitches for Critical and Life safety branch panels inspected and per plan. Provide Clearance to TEP ECO. |
| 01/14/2020 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Inspection of 10-480/277V>120/208V Transformers for Electrical rooms A & B Panels Approved. |
| 12/27/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Area A CT, X-Ray, and exam rooms Electrical in walls ok. |
| 12/11/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Area B Operating room, Electrical in walls from Isolated system ok. Also Inspected Putty packs at area B, where Fire Assembly Boxes required Fire barrier. |
| 12/09/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Two Trauma rooms and Isolation exam room area B ok. |
| 12/02/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
1- MC cables and metal boxes are okay to cover in walls for first floor Mosu rooms and Procedures rooms only. |
| 11/21/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Electrical in walls for Area B from GL (J.0-K.0/3.0-6.0). |
| 11/18/2019 |
ELECTRIC - INTERMEDIATE |
|
Partial Approval |
Electrical in Walls ok for Phase B from GL-L.0- 2.0 except Operating Room, I.T Room, & North Corridor. |