Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM02114
Permit Details
Apply Date:
03/16/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW APARTMENT BLDG
Contractors:
- TOFEL CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM02114
Permit Status: C of o
Permit Description: NEW APARTMENT BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/16/2017 | PLANS OK TO SUBMIT - COMM | 03/16/2017 | COMPLETED |
| 03/16/2017 | 3RD PARTY REVIEW - COMMERCIAL | 05/25/2017 | COMPLETED |
| 04/13/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 06/07/2018 | COMPLETED |
| 05/25/2017 | 3RD PARTY REVIEW - COMMERCIAL | 07/11/2017 | COMPLETED |
| 06/04/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 11/30/2018 | COMPLETED |
| 07/27/2017 | REVISION - - 1ST | 07/28/2017 | COMPLETED |
| 09/07/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 09/15/2017 | COMPLETED |
| 11/29/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 04/05/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM02114
Permit Status: C of o
Permit Description: NEW APARTMENT BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/16/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM02114
Permit Description: NEW APARTMENT BLDG
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2017 | PLUMBING - PRE SLAB | RCAMACHO | Approved | AFTER HOURS RECEIVED CHECK # 024272 $165.00 2ND HALF OF DECK POUR |
| 12/21/2017 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | LAST ENTRY 2017 5 EACH SECONDARIES CONDUIT FROM TRANSFORMER TO MPC 3 EACH 2 1/2" CONDUIT FROM SCSHP TO DECK SLAB 5 EACH 4" CONDUIT SECONDARIES FROM TRANSFORMER TO MPB |
| 06/07/2018 | ROOF NAILING | RCAMACHO | Approved | |
| 06/07/2018 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | |
| 08/27/2018 | PLUMBING - ROOF DRAINS | RCAMACH1 | Approved | IVRS - Inspection :* |
| 09/05/2018 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | |
| 09/07/2018 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 10/24/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 10/24/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 10/24/2018 | FRAMING | RCAMACHO | Approved | |
| 10/24/2018 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | NE retaining wall per detail ssk2 |
| 10/30/2018 | STUCCO MESH | RCAMACHO | Approved | |
| 11/01/2018 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | ECO ok to energize switchgear for test To remain locked out and tagged out |
| 11/01/2018 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | ECO ok to energize switchgear for test To remain locked out and tagged out |
| 11/29/2018 | SIGN - FINAL | bbenedo1 | Approved | |
| 11/29/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | Room 111 closets have a total of 3 heads that are twisted Room 111 bathroom has a head that needs to be replaced Room 110 Kitchen area has a head that needs to be tweaked Room 110 has a head in the bathroom that needs to be adjusted Mechanical room on the 1st floor east area needs to have a head added because it is covered with drywall Room 113 bedroom areas have 2 heads that need to be corrected Room 113 has a head in the closet that has tape on it and needs an escutcheon added Room 113 hallway head is painted and needs to be replaced Room 115 bathroom head needs to be adjusted/ replaced Room 104 has a painted head in the bathroom Room 105 laundry room has a painted head Room 107 head painted in the kitchen that also needs to be lowered since it is obstructed by the light fixture Room 107 painted heads in the laundry and bathroom areas Room 116 hall head needs to be corrected Room 116 closet and hall heads are painted Add head in the fire riser room Add heads under the garage door in the basement Add head in the mutli purpose room Remove two heads in the hall outside of the offices Rotate all hose connection so that they are not pointing in the down position. The bike room has two heads that are painted Need to extend the stanpipes to the roof for access This was for the first floor only |
| 11/29/2018 | RIGHT OF WAY - FINAL | cfarren | Approved | contractor would like to keep temp fence up for the project while they finish up landscaping for safety which will have to removed before final. they still have some scuppers to install in the sidewalk and will get another ROW permit to due those installs. they also have one panel of sidewalk that needs to be removed due to not being compliant on south ramp on the east side of the project along with patching a few chips in existing sidewalk. all of this will be done during scupper install, |
| 11/29/2018 | NPPO - FINAL | BBENEDON | Approved | |
| 11/30/2018 | STORMWATER FOLLOW-UP INSP | BBENEDON | Approved | Secure fence netting that has come loose along North perimeter. Clean mud from the sidewalks. Remove debris that is staged outside of the fenced area. |
| 11/30/2018 | LANDSCAPE - FINAL | BBENEDON | Approved | Complete Landscaping shown on development package, plants and trees missing, 4 in Basin around tree Wells required, provide staking. Contractor has not yet installed DG. |
| 11/30/2018 | ENGINEERING - FINAL | BBENEDON | Approved | Engineering has no issues preventing TCO. |
| 11/30/2018 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | Ok pending Armondo Q. approval |
| 11/30/2018 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
| 11/30/2018 | LANDSCAPE - FINAL | bbenedo1 | Approved | Work is in progress. |
| 12/18/2018 | MECHANICAL - ABOVE CEILING | IVR USER | Approved | IVRS - AP canceled |
| 12/18/2018 | PLUMBING - INTERMEDIATE | IVR USER | Approved | IVRS - AP canceled |
| 12/18/2018 | PLUMBING - ROUGH, SOIL | IVR USER | Approved | IVRS - AP canceled |
| 12/18/2018 | ZONING - FINAL | RSALDAT | Approved | On site inspection found that building elevations do not meet the IID concept drawings. |
| 12/19/2018 | SITE - SEWER | ESTEVENS | Approved | |
| 12/19/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 12/19/2018 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 12/19/2018 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 12/19/2018 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 12/19/2018 | SHEET ROCK NAILING | ESTEVENS | Approved | |
| 12/19/2018 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
| 12/19/2018 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 12/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 12/19/2018 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 12/27/2018 | TEP CLEARANCE - AM | RCAMACHO | Approved | ECO |
| 12/28/2018 | FIRE - FINAL | jvincent | Approved | APPROVED TO OBTAIN TCO FOR 3RD FLOOR. |
| 12/28/2018 | FIRE - FINAL | JPEELDAVIS | Approved | OK FOR TCO 3RD FLOOR |
| 12/28/2018 | MECHANICAL - FINAL | RCAMACHO | Approved | Terminate condensate lines terminate TPR lines secure dishwasher drain lines highest point anti-tilt stoves labels circuits seal opening sub panels except unit 302 not complete ok To apply for temporary CEO units 301, 303–319 only pending engineering and fire |
| 12/28/2018 | PLUMBING - FINAL | RCAMACHO | Approved | Terminate condensate lines terminate TPR lines secure dishwasher drain lines highest point anti-tilt stoves labels circuits seal opening sub panels except unit 302 not complete ok To apply for temporary CEO units 301, 303–319 only pending engineering and fire |
| 12/28/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | Terminate condensate lines terminate TPR lines secure dishwasher drain lines highest point anti-tilt stoves labels circuits seal opening sub panels except unit 302 not complete ok To apply for temporary CEO units 301, 303–319 only pending engineering and fire |
| 12/28/2018 | BUILDING - FINAL | RCAMACHO | Approved | Terminate condensate lines terminate TPR lines secure dishwasher drain lines highest point anti-tilt stoves labels circuits seal opening sub panels except unit 302 not complete ok To apply for temporary CEO units 301, 303–319 only pending engineering and fire |
| 01/24/2019 | FIRE - ALARM FINAL | gsereno1 | Approved |