Inspection History Details
Inspection Status: Approved
Inspection History: STUCCO MESH
Permit Number - T17CM02114
Inspection Description - STUCCO MESH
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2018 | STUCCO MESH | Approved | ||
| 10/19/2018 | STUCCO MESH | Partial Approval | Corridor 701 through 111, Corridor 113 through 117 | |
| 10/17/2018 | STUCCO MESH | Partial Approval | Horshoe and rooms 101-107 corridor | |
| 10/11/2018 | STUCCO MESH | Not ready for Inspection | ||
| 10/05/2018 | STUCCO MESH | Partial Approval | South wall except stairwell wall | |
| 10/03/2018 | STUCCO MESH | Not ready for Inspection | ||
| 09/28/2018 | STUCCO MESH | Partial Approval | Completion of 4th floor corridors only | |
| 09/20/2018 | STUCCO MESH | Partial Approval | North corridor from unit 401-407 | |
| 09/06/2018 | STUCCO MESH | Not ready for Inspection | ||
| 08/29/2018 | STUCCO MESH | Partial Approval | Playground area south walls all 4 floors only | |
| 08/28/2018 | STUCCO MESH | Partial Approval | playground area east north and west walls all four levels 2nd level corridor from units 201 to 215 only |
|
| 07/19/2018 | STUCCO MESH | Partial Approval | UNITS 107-111, 207-211,307-311 & 407-411 ONLY | |
| 06/28/2018 | STUCCO MESH | Partial Approval | COURTYARD NORTH WALLS ALL 4 FLOORS ONLY | |
| 06/15/2018 | STUCCO MESH | Partial Approval | NORTH WALL UP TO ROOM 107 ALL 4 FLOORS ONLY |