Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM02114

Parcel: 116206330


Addresses:

855 W CONGRESS ST


Inspection Status: Approved

Inspection History: ELECTRIC - FINAL

Permit Number - T17CM02114

Inspection Description - ELECTRIC - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
01/24/2019 ELECTRIC - FINAL Approved
01/23/2019 ELECTRIC - FINAL Partial Approval Units 401 - 406 and 408 - 410 only
pending fire and engineering finals
01/17/2019 ELECTRIC - FINAL Partial Approval level 2 only pending fire final
OK to apply for temporary C of O level 2
01/07/2019 ELECTRIC - FINAL Partial Approval unit 401 through 416 OK to clear meters only
12/28/2018 ELECTRIC - FINAL Partial Approval Terminate condensate lines
terminate TPR lines
secure dishwasher drain lines highest point
anti-tilt stoves
labels circuits
seal opening sub panels
except unit 302 not complete
ok To apply for temporary CEO units 301, 303–319 only
pending engineering and fire
12/26/2018 ELECTRIC - FINAL Partial Approval Units 201-215 OK to clear meters Eco
12/17/2018 ELECTRIC - FINAL Partial Approval Ok to clear meters 301- 315
Units 115, 113, 110, 109, 108, 106, 104, 103, 101, and 102 only
12/05/2018 ELECTRIC - FINAL Partial Approval Ok to clear meters to units 301-319
11/29/2018 ELECTRIC - FINAL Partial Approval For unit 107, 105, 114, 116, 111 only
11/13/2018 ELECTRIC - FINAL Partial Approval Ok to energize units 101 -117 only
11/08/2018 ELECTRIC - FINAL Not ready for Inspection Canceled by Nick
11/07/2018 ELECTRIC - FINAL Partial Approval MP-A, MP-B & MP-C OK TO ENERGIZE FOR TEST (ECO)

Individual meters to be cleared at time of final inspection
11/01/2018 ELECTRIC - FINAL Partial Approval ECO
ok to energize switchgear for test
To remain locked out and tagged out