Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM02114

Parcel: 116206330


Addresses:

855 W CONGRESS ST


Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T17CM02114

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
01/25/2019 PLUMBING - FINAL Approved CHLORINATION REPORT COMPLETED AND SENT TO RECORDS
01/24/2019 PLUMBING - FINAL Partial Approval Pending fire final, Pending engineering final And any as builts.
Pending air balance report and sterilization report to Bob Sherry 8:00 a.m. to 9:30 a.m.
01/23/2019 PLUMBING - FINAL Partial Approval Units 401 - 406 and 408 - 410 only
pending fire and engineering finals
01/17/2019 PLUMBING - FINAL Partial Approval level 2 only pending fire final
OK to apply for temporary C of O level 2
12/28/2018 PLUMBING - FINAL Partial Approval Terminate condensate lines
terminate TPR lines
secure dishwasher drain lines highest point
anti-tilt stoves
labels circuits
seal opening sub panels
except unit 302 not complete
ok To apply for temporary CEO units 301, 303–319 only
pending engineering and fire
12/19/2018 PLUMBING - FINAL Partial Approval OK to clear meters unit 216, 217, 218 and 219 only ECO
12/17/2018 PLUMBING - FINAL Partial Approval Ok to clear meters 301- 315
Units 115, 113, 110, 109, 108, 106, 104, 103, 101, and 102 only
11/30/2018 PLUMBING - FINAL Not ready for Inspection Cancelled
11/30/2018 PLUMBING - FINAL Partial Approval CHLORINATION REPORT OK JUST FOR 1ST FLOOR
11/29/2018 PLUMBING - FINAL Partial Approval For unit 107, 105, 114, 116, 111 only
06/29/2018 PLUMBING - FINAL Not ready for Inspection