Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
Permit Number - T17CM02114
Inspection Description - PLUMBING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/25/2019 | PLUMBING - FINAL | Approved | CHLORINATION REPORT COMPLETED AND SENT TO RECORDS | |
| 01/24/2019 | PLUMBING - FINAL | Partial Approval | Pending fire final, Pending engineering final And any as builts. Pending air balance report and sterilization report to Bob Sherry 8:00 a.m. to 9:30 a.m. |
|
| 01/23/2019 | PLUMBING - FINAL | Partial Approval | Units 401 - 406 and 408 - 410 only pending fire and engineering finals |
|
| 01/17/2019 | PLUMBING - FINAL | Partial Approval | level 2 only pending fire final OK to apply for temporary C of O level 2 |
|
| 12/28/2018 | PLUMBING - FINAL | Partial Approval | Terminate condensate lines terminate TPR lines secure dishwasher drain lines highest point anti-tilt stoves labels circuits seal opening sub panels except unit 302 not complete ok To apply for temporary CEO units 301, 303–319 only pending engineering and fire |
|
| 12/19/2018 | PLUMBING - FINAL | Partial Approval | OK to clear meters unit 216, 217, 218 and 219 only ECO | |
| 12/17/2018 | PLUMBING - FINAL | Partial Approval | Ok to clear meters 301- 315 Units 115, 113, 110, 109, 108, 106, 104, 103, 101, and 102 only |
|
| 11/30/2018 | PLUMBING - FINAL | Not ready for Inspection | Cancelled | |
| 11/30/2018 | PLUMBING - FINAL | Partial Approval | CHLORINATION REPORT OK JUST FOR 1ST FLOOR | |
| 11/29/2018 | PLUMBING - FINAL | Partial Approval | For unit 107, 105, 114, 116, 111 only | |
| 06/29/2018 | PLUMBING - FINAL | Not ready for Inspection |