Inspection Status: Approved
Inspection History: RIGHT OF WAY - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 11/29/2018 |
RIGHT OF WAY - FINAL |
|
Approved |
contractor would like to keep temp fence up for the project while they finish up landscaping for safety which will have to removed before final. they still have some scuppers to install in the sidewalk and will get another ROW permit to due those installs. they also have one panel of sidewalk that needs to be removed due to not being compliant on south ramp on the east side of the project along with patching a few chips in existing sidewalk. all of this will be done during scupper install, |