| 01/24/2019 | FIRE SPKLR - FINAL | Approved | ||
| 01/23/2019 | FIRE SPKLR - FINAL | Partial Approval | Inspected 4th floor. Several corrections shall be made prior to next inspection. Re-inspection fee is added. | |
| 01/22/2019 | FIRE SPKLR - FINAL | Partial Approval | 2nd floor complete and okay for TCO | |
| 01/17/2019 | FIRE SPKLR - FINAL | Denied | Re-inspection fee added for next inspection. 2nd floor TCO inspection not granted. *219 - Replace missing escucheon in closet *219/218 or 217 fill in gap in closet *217 MB escucheon * 215 front closets (painted heads) taped, escucheon missing * 214 seal gap * 211 painted head right hallway * 210 escucheon missing, painted head * 209 missing light fixture in bathroom * 208 escucheon missing front closet * 207 sprinkler needs to be recessed * 206 painted head, sink missing - Make sure caps and tape are off FA horns and extinguishers in place. |
|
| 11/29/2018 | FIRE SPKLR - FINAL | Partial Approval | Room 111 closets have a total of 3 heads that are twisted Room 111 bathroom has a head that needs to be replaced Room 110 Kitchen area has a head that needs to be tweaked Room 110 has a head in the bathroom that needs to be adjusted Mechanical room on the 1st floor east area needs to have a head added because it is covered with drywall Room 113 bedroom areas have 2 heads that need to be corrected Room 113 has a head in the closet that has tape on it and needs an escutcheon added Room 113 hallway head is painted and needs to be replaced Room 115 bathroom head needs to be adjusted/ replaced Room 104 has a painted head in the bathroom Room 105 laundry room has a painted head Room 107 head painted in the kitchen that also needs to be lowered since it is obstructed by the light fixture Room 107 painted heads in the laundry and bathroom areas Room 116 hall head needs to be corrected Room 116 closet and hall heads are painted Add head in the fire riser room Add heads under the garage door in the basement Add head in the mutli purpose room Remove two heads in the hall outside of the offices Rotate all hose connection so that they are not pointing in the down position. The bike room has two heads that are painted Need to extend the stanpipes to the roof for access This was for the first floor only |
|
| 07/10/2018 | FIRE SPKLR - FINAL | Partial Approval | 1st floor all rooms have had the 200 psi for two hour test. 2nd floor corridor has been looked at but ony had 50 psi of street pressure and will need the 200 test before the rest of the rooms can be sheet rocked. Ok to sheet tock the hall ways on the 2nd floor. |