Permit: T17CM02114

Parcel: 116206330


Addresses:

855 W CONGRESS ST


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T17CM02114

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
12/19/2018 EXCAVATION/LAYOUT REBAR & ZON Approved
12/12/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WORK NOT COMPLETE
12/12/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS
RECEIVED CHECK # 024272 $165.00
2ND HALF OF DECK POUR
12/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM 1 @ LEASING OFFICE TO GRID LINE 1B ONLY PER DETAIL SSK4
12/07/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TRASH ENCLOSURE CMU FOOTER
SC-4 PER DETAIL 222 CMU FOOTING
DECK SLAB GRID LINES 1B TO 7B FROM 10' WEST OF 4A TO 8A ONLY
12/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 11 EACH CF-1 CAISSONS SE OF LEASING OFFICE ONLY
12/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WF-1 STEM WALL AT NORTH CANTILEVER AREA ONLY
11/30/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 EACH F-3 FOOTERS PER DETAIL 119 GRID LINE 6A SOUTH OF 1B
WF-1 FOOTINGS GRID LINE 6B FROM 6.5 TO 3.5 NORTH CANTILEVER AREA
11/29/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WORK NOT COMPLETE ENOUGH TO INSPECT
11/21/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-4 AND F-5 FOOTERS AT PT SLAB CLUBHOUSE 16 FOOTERS ONLY
11/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 12 cages per SSK-3 ok, provide wet stamp from engineer and C.O.T approval prior to pour
11/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RAMP SLAB AND DRAIN ONLY
SEE TRENCH DRAIN DETAIL
10/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LOWER LEVEL WEST RAMP WALL
GARAGE ENTRY WING WALLS TO 9' ONLY
10/23/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LAST SECTION LOWER LEVEL SOUTH WALL GRID LINE 1B FROM 2A TO 3A PER DETAIL 104 ONLY
10/19/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SE CORNER LOWER LEVEL WAWLL PER DETAIL 104 AND STQIRWALL
10/18/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RAMP STEM PER DETAIL 219 AND 207 AT EAST RAMP WALL
10/17/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CL 1/B-3/A to5/A , east perimeter wall lower level , south half ramp wall east side ok
10/12/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXTERIOR WALLS PER DETAIL 104
SEE HIGHLIGHTED AREA ON S/01
10/10/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CC-1 COLUMNS 2/A/5B, 2A/5B, 2A/3B, 3A/5B, 3A/3B, 3A/2B, 4A/5B, 4A/3B, 4A/2B, 5A/4B, 5A/2B, 6A/4B, 6A/2B
NORTH WALL GRID LINE 6B FROM 3A TO 5A.25 LOWER LEVEL ONLY
10/09/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED
10/06/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CC-1 COLUMNS 5A/5B, 6A/5B,4A/4B, 5A/4B, 6A/4B AND 3A/4B ONLY
10/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval lower level west wall as indicated on plans ok
lower level columns 5B/2,3,4 A
10/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXTERIOR WALLS PER DETAIL 104 AND KEYNOTE 1 SEE HIGHLIGHTED AREA ON S101
10/03/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CC-1 COLUMNS STEEL ONLY COLUMNS 2A/5B, 3A/5B AND 3A/4B ONLY
CC-1 COLUMNS OK TO POUR 3B/2A, 3B/3A AND 4B/2A ONLY
10/02/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CC-1 COLUMNS 3B/2A, 3B/3A, 3B/4A AND 4B/2A STEEL ONLY
09/29/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval stem wall at elevator pits
column base at B.5/A.2
09/29/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WF-3 AND WF-4 FOOTERS AT GRID LINE 2A FROM 2B TO SOUTH RAMP FOOTERS
NOTE 11 FOOTERS GRID LINE2B SOUTH FROM 1A TO 2A TO INCLUDE F-2 FOOTER
09/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval lower level perimeter and spread footers at garage ok to pour
09/22/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection PRECON MEETING