Permit: T16CM07308
Permit Details
Apply Date:
09/22/2016
Applicant:
N/A
Description:
HOTEL
Architects:
- FRANKS, MICHAEL WILLIAM
Contractors:
- H S L CONSTRUCTION SERVICES L L C
Permit Reviews
Permit Number - T16CM07308
Permit Status: C of o
Permit Description: HOTEL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 07/03/2018 | COMPLETED |
07/03/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 07/05/2018 | COMPLETED |
07/12/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 07/16/2018 | COMPLETED |
09/22/2016 | PLANS OK TO SUBMIT - COMM | 09/26/2016 | COMPLETED |
09/23/2016 | 3RD PARTY REVIEW - COMMERCIAL | 12/07/2017 | COMPLETED |
12/07/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 02/09/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07308
Permit Status: C of o
Permit Description: HOTEL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/22/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07308
Permit Description: HOTEL
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJones | Approved | Bond Beam Approved |
05/07/2018 | PLUMBING - ROUGH, SOIL | BJones | Approved | |
05/07/2018 | BUILDING PRE-SLAB | BJones | Approved | |
05/08/2018 | FIRE SPKLR - FINAL | BJones | Approved | |
05/10/2018 | SITE - SEWER | BJONES | Approved | |
05/10/2018 | PLUMBING - SEWER HCS CONNECT | BJONES | Approved | |
06/22/2018 | ELECTRIC - UNDERGROUND | B JONES | Approved | CIRCUITS 36 AND 38 FOR LIGHT POLES |
07/11/2018 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN1 | Approved | OK TO POUR PART 1 OF THE LIGHT POLE BASES. CAN'T POUR ALL DUE TO RAIN WASHING MANY OF THEM OUT. |
09/07/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* 1- 2ND FLOOR EXTERIOR SHEAR WALL PANELS ARE OKAY. 2- 2ND FLOOR INTERIOR SHEAR WALL PANELS ARE OKAY, HOLD DOWNS IN PLACE. 3- 2ND FLOOR H2.5 AND A-35 CLIPS PROVIDED. 4- OKAY TO SHEET ROCK TUB AND SHOWER SURROUNDS. |
10/19/2018 | PLUMBING - GAS PRESSURE TEST | BJONES | Approved | Gas line installed per plan, then changed to accomidate location modification of heater. |
10/19/2018 | PLUMBING - GAS PRESSURE TEST | BJONES | Approved | |
11/05/2018 | BUILDING ABOVE CEILING | TVALENCIA | Approved | 1- 1st and 2nd floor DWV system and overhead and in wall domestic water distribution okay to cover. 2- Note; this inspection is for the 1st and 2nd floor king studios only. |
11/19/2018 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | 2ND FLOOR EXHAUST FANS OK |
11/21/2018 | ROOF NAILING | BJONES | Approved | Entire roof inspected for nailing per Plan 6” by 12” on center. |
11/26/2018 | STUCCO MESH | DMUNIZ | Approved | SOUTH SIDE OF BUILDING |
12/14/2018 | SHEET ROCK NAILING | BJONES | Approved | 1st floor Ok OK to sheet rock 3rd floor Bathroom Lids Mech exhaust ok to cover |
12/14/2018 | PLUMBING - ROOF DRAINS | BJONES | Approved | |
12/17/2018 | ELECTRIC - INTERMEDIATE | BJONES | Approved | 3rd Floor Intermediate Elect ok |
12/18/2018 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | 3rd floor, 8 rooms ok east side of building. |
12/20/2018 | MECHANICAL - ABOVE CEILING | BJONES | Approved | 2nd floor East of elevator Ok to Cover |
12/20/2018 | ELECTRIC - ABOVE CEILING | BJONES | Approved | 2nd floor East of elevator, OK to Cover |
12/21/2018 | FRAMING | DQUINN | Approved | Elevator shaft fire tape ok |
12/21/2018 | PLUMBING - ABOVE CEILING | DQUINN | Approved | 3rd floor dwv, west of elevator ok |
02/08/2019 | ELECTRIC - CABLE DROP | DQUINN | Approved | Clear eco Ok to set main service meter for hotel |
02/11/2019 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
04/05/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
04/05/2019 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Clear Southwest Gas |
05/02/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
05/07/2019 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | |
05/07/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
05/07/2019 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | |
05/07/2019 | U VALUE FOR WINDOW | DMUNIZ | Approved | |
05/07/2019 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | |
05/07/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
05/07/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
05/09/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
05/09/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
05/20/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
05/20/2019 | NPPO - FINAL | RLEDONNE | Approved | |
05/20/2019 | SIGN - FINAL | RLEDONNE | Approved | |
05/20/2019 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
06/05/2019 | BUILDING - FINAL | JGARCIA1 | Approved | |
06/05/2019 | RIGHT OF WAY - FINAL | DROBERTS | Approved | |
06/05/2019 | FIRE - FINAL | JPEELDAVIS | Approved | Per MAshford the phones provided at the elevator landings meet the intent of the two way communication. HSL knows that if they remove the phones they will no longer be code compliant. Tested the ERRC today and everything passed. Approved for C of O |